Search decisions

Use this page to find information regarding recent decisions that have been taken by the council’s decision making bodies.

Alternatively you can visit the officer decisions page for information on officer delegated decisions that have been taken by council officers.


Decisions published

30/04/2021 - Public Space Protection Order – Hobson Street, Failsworth ref: 4184    Recommendations Approved

The purpose of this report is to seek approval to make a Public Spaces Protection Order pursuant to powers contained in Sections 59 to 65 of the Anti-Social Behaviour, Crime and Policing Act 2014. The proposed terms of the Order are the installation of gates on the highway, as detailed on the map in Schedule 1 and the imposition of restrictions upon other behaviours within the gated area, as detailed in Schedule 2.

Decision Maker: Cabinet Member - Housing and Licensing and Statuory Deputy Leader

Decision published: 30/04/2021

Effective from: 11/05/2021

Decision:

RESOLVED - That the preferred option is the making of the Public Spaces Protection Order with the terms detailed in Schedules 1 and 2 (Appendix 2).
The cost of erecting and installing the gates will be met by funding identified by the Elected Members for the Ward. This work will be undertaken by PG Fabrications at a total cost of £2394.
It is proposed to prevent access to all traffic (including pedestrian) with the exception of residents, persons with the residents’ permission, persons having a private right of access and the Statutory Undertakers.

Lead officer: Anthony Hynes


24/03/2021 - Decision to extend the ABEN Phase 3 contract to 30th June 2021 with an option to extend by a further 3 months ref: 4183    Recommendations Approved

Following a competitive tender process for Phase 3 of the provision of A Bed Every Night (ABEN) rough sleeper accommodation project in Oldham the successful tenderer was DePaul. DePaul were awarded two contracts to deliver services between 1st September 2020 and 31st March 2021 for the main ABEN cohort and rough sleepers with No Recourse to Public Funds.
GMCA, the body that funds and monitors ABEN schemes across Greater Manchester, have confirmed intention to continue the initiative through to the end of March 2022, but have yet to secure the full funding required for this period. GMCA are however optimistic that the final funding picture will be confirmed by June 2021.
Due to these unexpected circumstances it has not been possible to carry out a full re-procurement exercise within required timescales. It is therefore proposed that the current ABEN contract be modified and extended by three months, with an option to extend for a further three if needed, on existing terms to enable sufficient time for new Phase 4 funding to be confirmed and appropriate procurement activity to take place.

Decision Maker: Director of Economy

Decision published: 30/04/2021

Effective from: 24/03/2021

Decision:

RESOLVED - That:
Agree to extend the current ABEN Phase 3 contract and ABEN NRPF contracts by three months to 30th June 2021, with an option to extend for a further three months: This option would ensure there is no disruption to service users and provides a realistic timescale for commissioning and implementing the ABEN Phase 4 contract.

Lead officer: Fiona Carr


17/03/2021 - Finance Service Restructure ref: 4177    Recommendations Approved

In order to achieve the saving of £389k within the 2021/22 approved budget it is proposed to restructure the Finance Service as set out in the finalised consultation document.

Decision Maker: GM ICS Executive Place Lead

Decision published: 22/04/2021

Effective from: 17/03/2021

Decision:

RESOLVED - That:1)To implement the proposed revised structure and ensure delivery of the full £389k savings for 2021/22 (plus £17k contributing to the corporate budget reduction)

Lead officer: Anne Ryans


20/04/2021 - Award and allocation of Priority Programme and Community Cohesion Funding to the voluntary, community and faith sector in 2021/22 ref: 4182    Recommendations Approved

The purpose of this report is to seek approval to award grant funding to the voluntary, community and faith sector, during the financial year 1st April 2021 to 31st March 2022, as identified at Appendix 1.

Decision Maker: Director of Economy

Decision published: 20/04/2021

Effective from: 20/04/2021

Decision:

RESOLVED - That the proposed allocations are awarded in 2021/22 as outlined at Appendix 1.

Lead officer: Natalie Downs


13/04/2021 - Exemption from Contract Procedure Rules – Contract Extension for locally commissioned service: Primary Care LARC Provision ref: 4181    Recommendations Approved

The purpose of this report is to seek an exemption from the contract procedure rules as stated in 21.3 (j) of the rules:
Where an extension for a particular period can be justified, for example where a Service review includes the intention to co-terminate relevant Contracts within a reasonable period.
This will ensure continued provision of Long Acting Reversible Contraception (LARC) via Primary Care (General Practices) signed up to deliver the scheme for the period 1 April 2021 to 31 March 2022 and to align future commissioning activity with the tendering exercise for the Integrated Sexual Health Service which is due to go out to tender during financial year 2021/22 with a contract start date of 1 April 2022.

Decision Maker: Director of Economy

Decision published: 20/04/2021

Effective from: 13/04/2021

Decision:

RESOLVED - That: Approve an exemption under clause 21.3 (j) of the contract procedure rules: Where an extension for a particular period can be justified, for example where a Service review includes the intention to co-terminate relevant Contracts within a reasonable period.

Lead officer: Andrea Entwistle


13/04/2021 - Exemption from Contract Procedure Rules – Contract Extension for locally commissioned Community Pharmacy Sexual Health provision ref: 4180    Recommendations Approved

The purpose of this report is to seek an exemption from the contract procedure rules as stated in 21.3 (j) of the rules:
Where an extension for a particular period can be justified, for example where a Service review includes the intention to co-terminate relevant Contracts within a reasonable period.
This will ensure continued provision of free Emergency Hormonal Contraception from Oldham community pharmacies signed up to deliver the scheme for the period 1 April 2021 to 31 March 2022 and will align future commissioning activity with the tendering exercise for the Integrated Sexual Health Service which is due to go out to tender during financial year 2021/22 with a contract start date of 1 April 2022.

Decision Maker: Deputy Chief Executive -

Decision published: 20/04/2021

Effective from: 13/04/2021

Decision:

RESOLVED - That: Approved an exemption under clause 21.3 (j) of the contract procedure rule document and extend the current contract for 1 year to co-terminate at the same time as the Integrated Sexual Health Services contract

Lead officer: Andrea Entwistle