Heat Network Early Works – appointment of 3DTD consultants

To appoint 3DTD consultants to deliver RIBA Stages 3, 4, 5 and 6 design for the proposed
Town Centre Heat Network Early Works, to be funded from the Council’s £7.8m Green Heat
Network Fund Construction Grant.
The value of the appointment is £679,595.12 inclusive of Bloom 5% fee and VAT. The value of
this appointment makes it a Key Decision. The Cabinet report of 26 February 2024 delegates
authority to the Deputy Chief Executive (Place) to make this appointment.

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 03/12/2025

Decision due: 14 Nov 2025 by Director of Communities

Lead member: Cabinet Member - Finance, Corporate Services and Sustainability and Deputy Leader

Contact: Andrew Hunt, Strategy Partnerships and Policy Manager Email: andrew.hunt@oldham.gov.uk Email: andrew.hunt@oldham.gov.uk.