Grid Connection Works for Wrigley Head Solar Farm

To award a contract for works for the grid connection for Wrigley Head Solar Farm to Electricity North West Limited (ENWL), at a cost of circa £170K. Given the exclusive nature of this work and specialist provision from the Distribution Network Operation for North West England, this work needs exemption approval from the Council’s Contract Procedure Rules.

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 30/10/2023

Decision due: 3 Jul 2023 by Cabinet Member - Finance, Corporate Services and Sustainability and Deputy Leader

Contact: Andrew Hunt, Strategy Partnerships and Policy Manager 0161 770 6587, Email: andrew.hunt@oldham.gov.uk Email: andrew.hunt@oldham.gov.uk.

Consultation process

Consultation has taken place with the Deputy Chief Executive, Director of Economy and the Executive Director for Place and Economic Growth.