Issue details

Creating a Better Place – Spindles Enabling Works 1 Variation 11 - Spindles Mineshaft Remediation Works

On 25th July Cabinet gave approval to split workstreams for the Spindles Redevelopment into Project 1 (demolition of TJ Hughes, construction of a new market and events space and works to the roof) and Project 2 (redevelopment of internal retail units to create workspace).

As per the site investigation, a potential mineshaft was uncovered beneath the former TJ Hughes building. This mineshaft will need to be treated upon completion of the demolition of TJ Hughes, this will be in the form of grouting or capping.

In order to maintain programme it is recommended that this treatment to the mineshaft is instructed under the Enabling Works contract, this will allow works to commence on the new build as soon as the Main Works contract is executed, rather than having additional lead in times and impacting on programme.

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 30/10/2023

Decision due: 12 Apr 2023 by Cabinet Member - Culture and Leisure, Cabinet Member - Finance, Corporate Services and Sustainability and Deputy Leader, Leader of the Council and Cabinet Member for Growth, Chief Executive, Director of Finance, Director of Legal (Monitoring Officer), Executive Director Place (Deputy Chief Executive)

Lead member: Cabinet Member - Culture and Leisure, Cabinet Member - Finance, Corporate Services and Sustainability and Deputy Leader, Leader of the Council and Cabinet Member for Growth

Contact: Paul Clifford, Director of Economy Email: paul.clifford@oldham.gov.uk Email: paul.clifford@oldham.gov.uk.

Consultation process

N/A

Decisions