In February 2022 Cabinet approved a
Pre-Construction Services Agreement (PCSA) contract to be entered
into
On 25th July Cabinet gave approval to split workstreams for the
Spindles Redevelopment into Project 1 (demolition of TJ Hughes,
construction of a new market and events space and works to the
roof) and Project 2 (redevelopment of internal retail units to
create workspace).
Following the ground investigation and the works undertaken by
ENWL, a foul water drain was discovered which would have clashed
with the new sub-station that feeds the market, events and archive.
Prior to commencement of the new build works, it is therefore
necessary to divert the foul drain. It is recommended that this is
instructed under the EW1
contract to avoid the need to delay the construction of new build
contract at the point of Main Contract award.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 30/10/2023
Decision due: 12 Apr 2023 by Cabinet Member - Culture and Leisure, Cabinet Member - Finance, Corporate Services and Sustainability and Deputy Leader, Leader of the Council and Cabinet Member for Growth, Chief Executive, Director of Finance, Director of Legal (Monitoring Officer), Executive Director Place (Deputy Chief Executive)
Lead member: Cabinet Member - Culture and Leisure, Cabinet Member - Finance, Corporate Services and Sustainability and Deputy Leader, Leader of the Council and Cabinet Member for Growth
Contact: Paul Clifford, Director of Economy Email: paul.clifford@oldham.gov.uk Email: paul.clifford@oldham.gov.uk.