Creating a Better Place – Spindles Enabling Works 1 Variation 7 - Early Procurement of Site Accommodation for Market, Events and Archive

On 25th July Cabinet gave approval to split workstreams for the Spindles Redevelopment into Project 1 (demolition of TJ Hughes, construction of a new market and events space and works to the roof) and Project 2 (redevelopment of internal retail units to create workspace).
An Enabling Works contract was entered into relating to Project 1, referred to as Enabling Works 1 (EW1).
To maintain programme, it is necessary to ensure the site setup is suitable for the number of staff involved in piling, mine workings, M

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 26/04/2023

Decision due: 12 Apr 2023 by Cabinet Member - Culture and Leisure, Cabinet Member - Finance, Corporate Services and Sustainability and Deputy Leader, Leader of the Council and Cabinet Member for Growth, Chief Executive, Director of Finance, Director of Legal (Monitoring Officer), Executive Director Place (Deputy Chief Executive)

Lead member: Cabinet Member - Culture and Leisure, Cabinet Member - Finance, Corporate Services and Sustainability and Deputy Leader, Leader of the Council and Cabinet Member for Growth

Contact: Paul Clifford, Director of Economy Email: paul.clifford@oldham.gov.uk Email: paul.clifford@oldham.gov.uk.