Creating a Better Place – Spindles PCSA Extension

On 25th July Cabinet gave approval to split workstreams for the Spindles Redevelopment into Project 1 (demolition of TJ Hughes, construction of a new market and events space and works to the roof) and Project 2 (redevelopment of internal retail units to create workspace).
An Enabling Works contract was entered into relating to Project 1, referred to as Enabling Works 1 (EW1), to the value of £760,330.42
In order to maintain programme for the overall project, Willmott Dixon have requested several variations/early orders are placed under the EW1 contract.

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 10/03/2023

Decision due: 3 Mar 2023 by Leader of the Council and Portfolio Holder for Reform and Regeneration

Lead member: Cabinet Member - Communities and Culture, Cabinet Member - Finance and Corporate Resources, Leader of the Council and Portfolio Holder for Reform and Regeneration

Contact: Paul Clifford, Director of Economy Email: paul.clifford@oldham.gov.uk Email: paul.clifford@oldham.gov.uk.

Consultation process

The Project Board have been consulted and endorse the outlined approach set out in this report.