In March 2020 Japanese Knotweed Control (JKC)
were appointed to remove the Japanese Knotweed from the Council
owned land at Mersey Road North (MRN).
The start of works was delayed due to Covid-19 and subsequently
began in late July 2020.The contractor has now advised of a
significant increase in the scope of the works and is claiming
additional costs.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 23/12/2020
Decision due: 21 Dec 2020 by Deputy Chief Executive -
Lead member: Cabinet Member - Business, Employment and Enterprise
Contact: Liz Garsrud, Principal Surveyor Email: liz.garsrud@oldham.gov.uk Email: liz.garsrud@oldham.gov.uk.
Consultation process
Hollinwood Junction Board Members.