The purpose of this report is to seek approval
to accept the successful tender and award and enter into a contract
for the demolition of the former Saddleworth School, High Street,
Uppermill to D.Hughes Demolition
Decision Maker: Cabinet Member - Regeneration and Housing (Leader - Councillor Amanda Chadderton)
Decision published: 13/02/2023
Effective from: 02/02/2023
Decision:
RESOLVED - That: the Council seek to appoint D
Hughes Demolition
Lead officer: Angela Stewart
To award and enter into two contracts for
Detailed Project Development / Outline Business Case stage
feasibility consultancy (Project Manager
Decision Maker: Director of Economy – Paul Clifford
Decision published: 13/02/2023
Effective from: 24/01/2023
Decision:
RESOLVED - That:
Award the contract and enter into contracts with Arup and Womble
Bond Dickinson. Under this option, the contracts for PM / SE and
Legal support will be awarded to the successful bidders and the
work will commence in January 2023.
Lead officer: Andrew Hunt
To seek approval for the publication of
Oldham’s 2022 Brownfield Land Register.
Decision Maker: Cabinet Member - Regeneration and Housing (Leader - Councillor Amanda Chadderton)
Decision published: 09/02/2023
Effective from: 09/02/2023
Decision:
RESOLVED - That:
It is recommended to note the approach to determining sites to
include in Part 1 and 2 of the Brownfield Register; to approve a
2022 update of the Brownfield Land Register (Part 1 only) for
publication; and to delegate authority to make minor amendments and
updates to the register throughout the year, if required, to the
Executive Director for Place
Lead officer: Elizabeth Dryden-Stuart
The purpose of this report is to consider the
introduction of a prohibition of waiting restriction on Clock
Street to remove inconsiderate parking around the access/egress to
Nova Tissue Company.
Decision Maker: Executive Director for Place & Economic Growth - Emma Barton
Decision published: 09/02/2023
Effective from: 09/02/2023
Decision:
RESOLVED - That:
the prohibition of waiting restrictions are introduced in
accordance with the plan and schedule at the end of this
report
Lead officer: Jeannette Whitney
The purpose of this report is to consider the
introduction of a new prohibition of waiting restriction order on
Kensington Avenue, Royton
Decision Maker: Executive Director for Place & Economic Growth - Emma Barton
Decision published: 09/02/2023
Effective from: 09/02/2023
Decision:
RESOLVED - That:
a prohibition of waiting order be introduced in accordance with the
plan (47/A4/1681/1) and schedule at the end of this report
Lead officer: Jeannette Whitney
The purpose of this report is to consider the
introduction of a prohibition of waiting restriction on Stock Lane,
Chadderton to improve vehicle access to local businesses
Decision Maker: Executive Director for Place & Economic Growth - Emma Barton
Decision published: 09/02/2023
Effective from: 09/02/2023
Decision:
RESOLVED - That:
the prohibition of waiting restrictions are introduced in
accordance with the plan and schedule at the end of this
report
Lead officer: Jeannette Whitney
Report setting out information to determine
the Non-Domestic (Business Rates) Tax Base for 2023/24, using the
most up to date information and estimates available.
Decision Maker: Cabinet Member - Finance and Low Carbon (Deputy Leader - Councillor Abdul Jabbar)
Decision published: 08/02/2023
Effective from: 31/01/2023
Decision:
That the Deputy Leader and Cabinet Member for
Finance
Wards affected: (All Wards);
Lead officer: John Hoskins
Decision Maker: Cabinet
Made at meeting: 23/01/2023 - Cabinet
Decision published: 25/01/2023
Effective from: 23/01/2023
Decision:
The Chair agreed to accept an Item of Business, Family Hubs and Start for Life Programme as a matter of urgency in accordance with S.100 B (4) of the Local Government Act 1972; Urgent Cabinet approval was required to enable the Council to ensure the programme could start as soon as possible and the decision could not reasonably wait until the next Cabinet meeting.
Consideration was given to a report of the Managing Director, Children and Young People which sought approval of the receipt of funding from the Department for Education and Department of Social Care to support transition to a new model of care the principles and objectives of the Government’s Family Hubs and Start for Life Programme.
Authorisation was also sought to delegate authority to agree all spending decisions related to the Family Hubs to the Director of Education and Early Years and the Director of Public Health after consultation with the Cabinet Member for Children & Young People, noting the role of a new Early Years and Early Help strategic partnership and the Children’s Transformation Board in this process.
Oldham was one of seventy-five local authorities pre-selected by the Department for Education (DfE) for the Family Hubs and Start for Life Programme. To enable the project Oldham Council was to receive an indicative allocation of £3.48 million over three financial years of 2022-23, 2023-24 and 2024-25. The Oldham sign up form attached to this report detailed spending priorities identified for Oldham for this period.
A comprehensive delivery plan detailing indicative costings was completed with partners for submission to the DfE by the 31 December 2022 for final approval.
Options/alternatives considered
Option 1- Approve the recommendations set out in the report
Approve the receipt of the Family Hubs and Start for Life funding to support the transition to more integrated and accessible services that provide support to parents and carers and contribute to a reduction in inequalities in health and education outcomes for babies, children and families
Option 2 - Do nothing. This will result in loss of funding for Oldham to deliver the Family Hub & Start for Life Programme
RESOLVED – That the Cabinet would consider the commercially sensitive information at Item 17 before making a decision.
Decision Maker: Cabinet
Made at meeting: 23/01/2023 - Cabinet
Decision published: 25/01/2023
Effective from: 23/01/2023
Decision Maker: Cabinet
Made at meeting: 23/01/2023 - Cabinet
Decision published: 25/01/2023
Effective from: 23/01/2023
Decision Maker: Cabinet
Made at meeting: 23/01/2023 - Cabinet
Decision published: 25/01/2023
Effective from: 23/01/2023
Decision Maker: Cabinet
Made at meeting: 23/01/2023 - Cabinet
Decision published: 25/01/2023
Effective from: 23/01/2023
Decision:
Consideration was given to a report of the Director of Economy which sought approval to accept a grant of £2,153,354 from the Public Sector Decarbonisation Scheme Phase 3a for energy works at the Spindles, and to commence the works.
The Public Sector Decarbonisation Scheme was a UK Government funded programme, administered by Salix.
The Council has previously bid for PSDS grant funding (via a GMCA consortium) to the PSDS3a funding round, for decarbonisation works at the Spindles, including the installation of roof and wall insulation, glazing, solar PV and heat pumps. The grant funding was not awarded at that time, due to the overall funding envelope being exceeded by the time Salix received Oldham’s application (via GMCA)
However, in September 2022 Salix approached GMCA asking whether Oldham would still be looking for the funding, as the PSDS3 a programme was underspent after the first 12 months of operation.
The PSDS3a application form for Spindles had been updated to take into account changes to the proposed project over the past 12 months, and had now been approved by Salix, who have signed a Grant Agreement with GMCA for the grant funding. The actual grant amount received by GMCA from Salix will be £2,291,822. However, the GMCA will ‘top-slice’ this grant amount as a management fee (£138,468 or 6%) and the actual grant amount to be received from GMCA by Oldham will be £2,153,354.
The decarbonisation works at the Spindles would contribute to the carbon neutrality targets set out in the Oldham Green New Deal Strategy and would also support the “A Clean and Green Future” priority set out in the Corporate Plan. They are also forecast to save around £45K annually in energy costs at the complex.
The Spindles project had been offered £2,153,354 in grant funding against a total project value of £3,956,223, requiring a match funding element from the Council of £1,802,869. The grant funding has to be utilised by 31st March 2025.
Options/alternatives considered
Option 1 - Do not accept the grant. Under this option, the grant funding would not be accepted and the additional energy works proposed at the Spindles complex would not be implemented.
Option 2 - Accept the grant and commence works. Under this option, the Council will enter into a partnership agreement with GMCA for disbursal of the grant, and the works will be carried out by the Spindles project team already appointed for the wider renovation programme at the site.
RESOLVED -That the grant funding be accepted and the Council commence the works.
Decision Maker: Cabinet
Made at meeting: 23/01/2023 - Cabinet
Decision published: 25/01/2023
Effective from: 23/01/2023
Decision:
Consideration was given to a report of the Director of Environment which sought a decision on the preferred option for delivery of Wrigley Head Solar Farm.
The Solar Farm project was a 891kW ground mounted solar PV array at a Council-owned former industrial landfill site at Wrigley Head in Failsworth. The solar farm would improve the site, including in terms of biodiversity via wildflower planting and other measures, and would generate a significant amount of renewable energy, potentially contributing to the Council’s 2025 carbon neutrality target and / or the borough 2030 target. The project would save an average of 50 tonnes of CO2 per annum over the lifetime of the scheme and cost around £1.1 million to develop. The specification of the project was set in 2019 when the original feasibility work was done it was possible that with improvements in technology, the scheme could achieve 1MW of generating capacity.
In spring 2020, the impact of the coronavirus pandemic and national lockdown on the economy meant that the long-term outlook for wholesale electricity prices was revised downwards. The change in this assumption underlying the financial model for the solar farm meant that with the new outlook, the solar farm no longer showed a viable business case.
As a consequence, the project was considered by Cabinet in the summer of 2020 in the context of the Creating A Better Place capital programme review. A decision was taken at that time to stop work on the project.
Before work on the project was paused, a fee was paid to Electricity North West to accept a grid connection offer. A further ‘staged payment’ of around £35K was due in 2020 but was not paid as a consequence of the Cabinet decision to pause work on the project. Electricity North West have confirmed that the grid connection offer was still valid and have provided updated details in terms of grid connection costs and timescales.
The solar farm scheme was dependent upon a cable easement across third party owned land. Two adjoining landowners have indicated a willingness to grant a cable easement across their land, however, no terms have been agreed. It is expected that the third-party landowner would want a payment or the transfer of the council’s adjoining land for nil consideration for the grant of the easement.
In July 2019 at Full Council, a new 2025 carbon neutrality target for the Council was announced - to cover Council buildings and street lighting.
The Oldham Green New Deal Strategy (adopted in March 2020) confirmed the Council carbon neutrality target for 2025 and set an additional carbon neutrality target of 2030 for the borough as a whole.
According to methodology from Salix, it was estimated that Wrigley Head Solar Farm could save around 50 tonnes per annum of CO2. The outline financial model also showed that the project could generate an IRR of between 3.5% and 7% from savings on the Council’s energy bill. The expected lifetime of the solar farm is 30 years.
The project gained Planning Permission in December 2021, with a number of Planning Conditions attached relating to environmental surveys and the construction of a screening fence alongside the tram track, which was agreed with TfGM in order to remove their objection to the scheme.
Electricity North West have confirmed that the grid connection offer for the solar farm is still valid. ENWL are now waiting for the next ‘staged payment’ of around £35K for connection works already accepted (which was not made after the project was paused in 2020).
For the scheme to be taken forward, negotiations would need to resume with the third party landowners who own the land across which the cabling connecting the proposed solar farm to the ENWL grid connection point must pass. This will likely be done by ENWL as part of the grid connection works, rather than by the Council.
The GM Combined Authority recently set up a framework agreement for low carbon projects called the “Go Neutral” framework. This framework has a number of lots, including two lots relevant to the Wrigley Head solar farm project. Lot 4 is for Council-funded ground mounted solar and Lot 5 was for developer-led and funded hybrid low carbon projects on Council-owned land, which can include ground-mounted solar. The framework agreement was available to Oldham Council.
In September / October 2022, the Council tested the market for the Wrigley Head project by placing an Expression of Interest on both lots 4 and 5 of the Go Neutral framework. These EOIs were placed to attract market feedback in terms of the practical deliverability of the project (Lot 4) and the financial case for the project (Lot 5). The EOI process is now complete and attracted two returns on each of Lots 4 and 5.
One of the two respondents on Lot 4 stated that due to a rise in costs, the Council should increase the available budget for the scheme by 25%. This would mean that the estimated capital budget required to construct the solar farm will rise from £1,080,465 to £1,350,581. This is the most accurate estimate of project cost available at the time of writing. A final cost can only be established through a full procurement process – which is likely to take the form of a mini-competition on the GM Go Neutral framework.
It was estimated that a revenue budget of around £70K would be required to progress the scheme to construction stage. This figure comprised £35K for a ‘staged payment’ on the grid connection, and £35K for the procurement and appointment of an ‘owners engineer’ in accordance with Contract Procedure Rules to act as a ‘client side’ external Project Manager for the scheme, overseeing the ‘Engineer, Procure and Construct’ (design and build) contractor.
Options/alternatives considered
Option 1 - Do nothing. Under this option, no further work would take place on the project, and no further expenditure would be incurred. However, the project would not generate a revenue income for the Council nor make any contribution to reducing carbon emissions in Oldham, GM nor generate electricity for a future Oldham Local Energy Market.
Option 3 - Proceed with a mini-competition under Lot 5 of the GM Go Neutral framework and procure the Owner’s Engineer. Under this option, the Council would seek a contractor funded and operated model for delivery of the Wrigley Head solar farm, with the Council purchasing electricity from the developer via a Power Purchase Agreement at a rate yet to be determined.
RESOLVED – That:
1. The preferred delivery option to proceed with a mini-competition under Lot 4 of the GM Go Neutral framework and procure the Owner’s Engineer. Under this option, the Council would see a contractor to design, build and operate the solar farm, which would be funded and owned by the Council, with the Council receiving the electricity generated via a Power Purchase Agreement with the Council’s main electricity supplier be agreed and the allocation of £1,350,581 capital funding from the Creating a Better Place programme for construction of the project be approved.
2. The appointment of a contractor further to a mini-competition on the GM Go Neutral framework delegated to the Director of Economy and the appointment of an Owner’s Engineer in consultation with the Executive Director for Place and Economic Growth, the Leader of the Council, the Cabinet Member for Finance and Low Carbon, the Chief Executive and the Directors of Finance and Legal Services.
3. The acceptance of any grant funding from the Unlocking Clean Energy in Greater Manchester project be delegated to the Director of Economy in consultation with the Executive Director for Place and Economic Growth, the Leader of the Council, the Cabinet Member for Finance and Low Carbon, the Chief Executive and the Directors of Finance and Legal Services.
Decision Maker: Cabinet
Made at meeting: 23/01/2023 - Cabinet
Decision published: 25/01/2023
Effective from: 23/01/2023
Decision:
Consideration was given to a report of the Leader of the Council which sought approval and adoption of the Oldham Transport Strategy.
The Oldham Transport Strategy set out how Oldham would meet the ambitions set out in the Greater Manchester Transport Strategy 2040 and sub strategies, whilst ensuring investment was prioritised to ensure Oldham’s Transport and Highways Network support a Healthy, Clean and Thriving borough.
The Vision for Oldham as set out in the strategy is to create a connected borough with increasing use of public transport and active travel that provides all people with safe and inclusive access to opportunities and healthy choices.
The Transport Strategy set out the council's transport and highways ambitions in relation to:
The Oldham Transport Strategy and Delivery Plan aligned with the Greater Manchester Transport Strategy 2040 ‘Right Mix’ ambition for half of all journeys to be made by active and sustainable transport modes by 2040. The aim of Oldham’s Transport Strategy was to reduce carbon emissions from transport, increase cycling, walking and public transport use and enable the borough to become an increasingly attractive place to live, work and visit.
The Delivery Plan set out transport interventions to be delivered over the following time periods:
The Transport Strategy also included the first proposed sub-strategy - an update to the Oldham Town Centre Parking Strategy. The refreshed Town Centre Parking Strategy was necessary to support the current regeneration proposals for the town centre.
Options/alternatives considered
Option 1 - To adopt and publish the Transport Strategy, Delivery Plan and Town Centre Parking Strategy to support our framework to direct transport investment for all modes going forward to support sustainable growth and development to enable and ensure a healthy, clean, safe and connected.
Option 2 - To not adopt and publish the Transport Strategy, Delivery Plan and Town Centre Parking Strategy, which will weaken the case for transport investment in the borough, as there will not be clear direction on the need and justification for the investment, and links to how it meets the targets set out in the GM2040 Strategy.
RESOLVED – That the Oldham Transport Strategy including the Delivery Plan and Oldham Town Centre parking strategy be adopted to embed meeting the aims of the Greater Manchester Transport Strategy 2040 (GM2040) in the borough and ensure our transport and highways networks enable the building of homes and the creation of jobs.
Decision Maker: Cabinet
Made at meeting: 23/01/2023 - Cabinet
Decision published: 25/01/2023
Effective from: 23/01/2023
Decision:
Consideration was given to a report of the Managing Director, Children and Young People which sought approval of a revised Local Academy Conversion Policy and Guidance and its application in all cases where maintained schools convert to academy status.
The original Local Authority Policy on Academy Conversion was agreed in 2016. In March 2022 the government released a new white paper ‘Opportunity for All’. A key aim of the white paper was to enable the conversion of all maintained school to academies by 2030.
In September 2022 the Department of Education also published new guidance on schools causing concern. In effect this means that schools that are currently meet the Department for Education definition of ‘coasting schools’ would be required to convert to academy status. The guidance was also clear that this process would be accelerated in areas that are designated as EIA (Priority Education Investment Areas). Oldham is one of four such areas within GM (Greater Manchester)
Options/alternatives
There are no suggested alternatives.
Academy Conversion Policy and Guidance and its application in all cases where maintained schools convert to academy status.
The original Local Authority Policy on Academy Conversion was agreed in 2016. In March 2022 the government released a new white paper ‘Opportunity for All’. A key aim of the white paper is to enable the conversion of all maintained school to academies by 2030. In September 2022 the Department of Education also published new guidance on schools causing concern.
RESOLVED – That:
1. The attached Local Authority policy on Academy Conversion and Guidance for Schools be approved by Cabinet and distributed to all maintained schools within the borough.
2. Authority be given to the Director of Education and Early Years and the Cabinet Member for Education to authorise all associated agreements in respect of academy conversions and approve any changes to the policy resulting from changes to primary legislation.
Decision Maker: Cabinet
Made at meeting: 23/01/2023 - Cabinet
Decision published: 25/01/2023
Effective from: 23/01/2023
Decision:
Consideration was given to a report of the Director of Finance which presented to the Cabinet the Council Tax Tax Base and provisional Non-Domestic Rates (NDR) Tax Base forecast for 2023/24 which would underpin the forthcoming Council Budget and Medium-Term Financial Strategy scheduled for consideration at Budget Council on 1 March 2023.
The report also sought delegated authority to finalise the 2023/24 Non-Domestic Rates (Business Rates) forecast to reflect up to date Non-Domestic Rates details to be submitted to Central Government via the annual NNDR 1 return by the statutory deadline of 31 January 2023.
The technical report provided information on the Council Tax Tax Base for 2023/24 using the most up to date valuation list and all other information and estimates available.
The total number of chargeable properties included in the Council Tax Tax Base calculation in Oldham for 2023/24 was 95,980. This figure was reduced to 87,000 after allowing for discounts and exemptions and translated to the equivalent of 69,175.3 Band D properties. After applying adjustments for the Local Council Tax Support scheme offset by the additional charging for empty properties and an anticipated increase in the number of properties to be included in the valuation list over the forthcoming year, the number of Band D equivalent properties reduced to 60,465.1. The final Tax Base after the application of the anticipated collection rate of 96.75% was 58,500 which was an increase of 1,050 when compared to the Council Tax Tax Base for 2022/23 of 57,450.
The 2023/24 Tax Bases for Saddleworth and Shaw and Crompton Parish Councils of 8,952 and 5,615 respectively, had been calculated using the same methodology.
Statute requires local Billing Authorities to prepare and submit to the Department of Levelling Up, Housing and Communities (DLUHC) a locally determined and approved Business Rates forecast through the NNDR 1 return by 31 January each year. This forecast would be used to determine the 2023/24 “demand” and payment schedule for Business Rates between Oldham Council and the Greater Manchester Combined Authority (GMCA). Being a participant in the Greater Manchester 100% Rates Retention Pilot Scheme which was confirmed for the financial year 2023/24 in the Provisional Local Government Finance Settlement (PLGFS) which was announced on 19 December 2022 means the Council no longer pays a share of Business Rates to Central Government. Instead, Oldham currently retains 99% of the income with 1% being paid to the GMCA for Fire and Rescue services.
The estimated rating income for 2023/24 attributable to Oldham Council using the latest information which includes the Business Rates Revaluation was currently £48.499m which was a decrease of £0.106m compared to 2022/23. Delegation is sought to enable the Business Rates forecast to be updated to take account of up-to-date Non-Domestic Rates information, enabling the submission to Central Government of the annual NNDR 1 return by the statutory deadline of 31 January 2023.
As the 100% Business Rates retention regime was continuing, the Council had assumed a benefit of £4.180m from the pilot scheme for 2023/24. The current arrangement was that the Council could retain 75% of this benefit with the balance attributable to GMCA. The Council’s share, £3.135m would be made available to support the 2023/24 budget whilst the GMCA share would be transferred to a reserve to be paid to the GMCA once the final position had been agreed. The figures will only be confirmed by the end of 2023/24.
It was important to highlight to Members that the preparation of Council Tax and Business Rates Tax Bases was being undertaken in a period of unprecedented uncertainty and volatility. The current economic climate including uncertain prospects for economic growth, Government changes in policy in year, the revaluation of Business Rates from 1 April 2023 and the economic impact of the conflict in Ukraine are amongst the issues which made forecasting challenging.
The Collection Fund had moved into a projected surplus position in 2022/23 providing the opportunity to use the surplus to support the 2023/24. This was the result of the lifting of COVID-19 related restrictions during the year and consequent improved collection rates. It also reflected the level of Government support provided via Business Rate reliefs which has reduced any losses in collection.
Options/alternatives considered
The Council had little discretion in the calculation of the number of properties incorporated into the Council Tax Tax Base given the legislative framework that was in place. However, there was some discretion in estimating the number of new properties that would be included on the Council Tax register during 2023/24 and the change to the number of claimants of Council Tax Reduction. A prudent view had been taken in this regard. The main area for an alternative approach was over the level of assumed collection rate. An increase in the collection rate would boost the anticipated Council Tax income and a decrease in the rate would decrease income. The Council had chosen to maintain its 2023/24 collection rate at 96.75%. This decision had been influenced by prevailing economic circumstances and current trends in collection rates.
The NNDR1 return generated the figures upon which the Business Rates Tax Base is prepared. It was not, therefore appropriate to consider an alternative approach. However, as the figures included on the NNDR1 return on 31 January 2023 may vary from the estimated level, delegation was sought to allow the opportunity to revise the Business Rates forecast and approve a revised and more accurate position for budget setting.
RESOLVED – That:
1. The Council Tax Tax Base for 2023/24 at 58,500 Band D equivalent properties be approved.
2. The latest estimate for 2023/24 Business Rates revenue that was attributable to Oldham Council as being £48.499m be approved.
3. The drawing down from the Collection Fund of £4.180m of Business Rates retention gains anticipated for 2023/24, of which the Council would utilise £3.135m (75%) be approved.
4. The Tax Bases for Saddleworth and Shaw and Crompton Parish Councils of 8,952 and 5,615 respectively be noted.
5. The decision to vary the final Business Rates forecast and hence the Business Rates Tax Base, if required, be delegated to the Director of Finance in consultation with to the Deputy Leader and Cabinet Member for Finance and Low Carbon.
Decision Maker: Cabinet
Made at meeting: 23/01/2023 - Cabinet
Decision published: 25/01/2023
Effective from: 23/01/2023
Decision:
Consideration was given to a report of the Director of Environment which sought approval to award a new bulky waste collection and local welfare provision (LWP) contract to start 1st April 2023.
It was reported that the new contract was an attempt at combining two Council services, which were currently being operated under separate contracts.
The main aim of the new contract would be to develop financial and resource efficiencies whilst at the same time maximising the flow of bulky collected pre-loved furniture and white good items into the LWP scheme. The new contract would improve the Council’s ability to help and support the needs of vulnerable residents (in furniture poverty) when trying to establish or maintain a home in the borough.
Options/alternatives considered
Option 1 – To approve a new combined bulky collection & LWP contract be entered into with FRC (Bulky Bob’s).
Option 2 – To not award FRC a new contract and undertake a new procurement process with the aim of awarding two new separate contracts. There are no perceived operational benefits to this model.
Option 3 – To not award FRC with a new contract and continue as we are. This is not a viable option as both the current Bulky and LWP contracts require renewal and due to the costs associated, compliant contracts are required.
RESOLVED – That the Cabinet would consider the commercially sensitive information contained at Item 16 before making a decision.
Decision Maker: Cabinet
Made at meeting: 23/01/2023 - Cabinet
Decision published: 25/01/2023
Effective from: 23/01/2023
Decision:
Consideration was given to a report of the Executive Director, Place and Economic Growth, which sought to update the Cabinet on the present position of Site A Princes Gate, the current market conditions and future options.
The Council had received notification from Lidl that the changing market conditions in the hotel and leisure sector had resulted in them no longer being able to deliver the contracted agreement at the town centre site.
Subsequently, Lidl and the Council had agreed to progress a mutual surrender and termination of the existing agreement (between Oldham Council and Lidl UK GmbH dated 27th February 2019) reflecting the current market conditions.
Options/ alternatives considered
Option 1- Mutual surrender/termination of the agreement.
Option 2 - Unilateral termination by the Council.
Option 3 - Agree a variation of the existing contract. However, this was not
considered a viable option.
RESOLVED – That the Cabinet would consider the commercially sensitive information at Item 15 before making a decision.
To award and enter into the contract for
Detailed Project Development / Outline Business Case stage
feasibility consultancy for the proposed Oldham Town Centre
Minewater District Heat Network, to the value of
£179,700.
Decision Maker: Cabinet Member - Finance and Low Carbon (Deputy Leader - Councillor Abdul Jabbar)
Decision published: 25/01/2023
Effective from: 12/01/2023
Decision:
RESOLVED - That:
Option 2: Award the contract and enter into a contract with Buro
Happold Limited. Under this option, the contract for DPD / OBC
stage feasibility work will be awarded to the successful bidder and
the work will commence in January 2023.
Lead officer: Andrew Hunt
The purpose of this report is to consider the
implementation of road safety measures in the form of traffic
calming measures along the Salmon Fields
Decision Maker: Executive Director for Place & Economic Growth - Emma Barton
Decision published: 24/01/2023
Effective from: 01/02/2023
Decision:
RESOLVED - That:
the traffic calming measures associated with this scheme are
approved, in accordance with the plans and schedule at the end of
this report
Lead officer: Jeannette Whitney
This report recommends that land at Snipe
Clough be advertised advising of the Council’s intention to
dispose of public open space.
Decision Maker: Director of Economy – Paul Clifford
Decision published: 23/01/2023
Effective from:
Decision:
RESOLVED - That:
This report recommends proceeding with a stage 1 loss of Public
Open Space Report and be advertised advising of the Council’s
intention to dispose of public open space.
Any objections to the proposed disposal of the public open space
received will be contained in a future Stage 2 report with further
recommendations.
Land within Council ownership comprising c 5 acres at Snipe Clough
is categorised as Public Open Space.
The subject land has been identified by Northern Roots (Oldham)
Limited’s masterplan as being required to deliver a bike hub
open to the Public and an important part of this project’s
themes around outdoor activities
Lead officer: James Tolan