27/09/2022 - Burnley Lane, Chadderton North – 20mph speed limit and traffic calming scheme ref: 4560 Recommendations Approved
The purpose of this report is to seek approval
to formally advertise the traffic calming notices and traffic
regulation orders associated with the proposals as detailed in the
drawings and schedules at the end of this report.
Decision Maker: Executive Director for Place & Economic Growth
Decision published: 16/12/2022
Effective from: 27/09/2022
Decision:
RESOLVED - That:
To approve the formal advertising of the proposals as detail at the
end of this report and approve the implementation of the
measures
Lead officer: Alister Storey
15/09/2022 - Contract Award: Disabled Facilities Grant (DFG) Construction Framework ref: 4555 Recommendations Approved
To award the DFG Construction Framework for
the supply and installation of level access showers and shower over
baths for vulnerable people of all ages.
Decision Maker: Cabinet Member - Health and Social Care
Decision published: 30/11/2022
Effective from: 08/12/2022
Decision:
RESOLVED - To award the DFG Construction
Framework Agreement following a procurement exercise to the four
successful Contractors on a rotational basis:
1) M
Lead officer: Fateha Khanom
21/09/2022 - Housing Delivery Test Action Plan 2021 ref: 4525 Recommendations Approved
The Housing Delivery Test (HDT) Action Plan
2021 responds to the HDT Measurement 2021 result published in
January 2021. It is made up of two documents:
Part 1 – Set’s out the context, evidence and root
causes for housing under-delivery in Oldham
Part 2 – The Action plan itself
Decision Maker: Cabinet Member - Communities and Culture
Decision published: 17/10/2022
Effective from: 26/10/2022
Decision:
Publication of Housing Delivery Action Plan
2022 (Part One and Part Two) approved.
Wards affected: (All Wards);
Lead officer: Elizabeth Dryden-Stuart
15/09/2022 - Appropriate Adult Service for Children and Young People ref: 4502 Recommendations Approved
The contract for Appropriate Adult Service for
children and young people, for which Stockport Council is the lead
authority, is due to expire on 31st March 2023. The contract was
initially awarded in 2018 for a period of three years from 8 May
2018, with the option to extend twice, each time for a maximum of
one year.This paper is seeking approval to exercise the
option to re tender with the current specification and Inter
Authority Agreement .
Decision Maker: Managing Director Children and Young People (DCS)
Decision published: 28/09/2022
Effective from: 06/10/2022
Decision:
RESOLVED - That:
To approve the re-commissioning of the AAS with Stockport Council
acting as the lead authority. An Inter Authority Agreement will
govern the shared commission from 1st April 2023 for a period of
three years, with the option
to extend for up to an additional two years
Lead officer: Elizabeth Taylor
31/08/2022 - Modification to Extend the Contract for Enforcement Services ref: 4503 Recommendations Approved
To extend the Council's current working
arrangements with Marston’s Holdings Limited. and Rundle Co.
Ltd. for 7 months (from the 1st November 2022 to the 31st May
2023). The contracts will require modification as the current
contracts finish on 31st October 2022.
Decision Maker: Cabinet Member - Finance and Corporate Resources
Decision published: 27/09/2022
Effective from: 31/08/2022
Decision:
RESOLVED - That:To award a 7-month extension
to the current working arrangements to allow the Revenues Service
to develop a new 3-year contract based on an optimal balance
between in-house and external enforcement.
Lead officer: Anne Ryans
01/09/2022 - Decarbonisation of the estate ref: 4501 Recommendations Approved
To provide approval to progress four
initiatives supporting the decarbonisation of Council Buildings and
achievement of the 2025 carbon neutrality target set out in the
Oldham Green New Deal Strategy.
Decision Maker: Director of Economy
Decision published: 15/09/2022
Effective from: 23/09/2022
Decision:
RESOLVED - That:
Progress the four initiatives in this report as recommended. Under
this option, the four initiatives set out in this report will be
progressed, in support of achieving the Council’s 2025 carbon
neutrality target.
Lead officer: Andrew Hunt
13/09/2022 - St John Street, Lees - Proposed Bus Stop Clearways ref: 4500 Recommendations Approved
To remove obstructive parking from two bus
stops along St John Street that is preventing the less able to
board and alight the bus
Decision Maker: Cabinet Member - Neighbourhoods
Decision published: 15/09/2022
Effective from: 23/09/2022
Decision:
RESOLVED - That:
One bus stop is relocated from outside residential properties and
both stops be provided with bus stop clearway markings.
Lead officer: Gordon Anderson
08/09/2022 - Commissioning of contractor to produce Opportunity Area early years and mental health thematic evaluation report. ref: 4498 Recommendations Approved
A decision is sought to request approval for a
contract to be directly award to:
1. Better Communication CIC to carry out research and evaluation to
produce thematic Early Years report.
2. Centre for Applied Education Research (CAER) to carry out
research and evaluation to produce thematic Mental Health
report.
Decision Maker: Director of Education, Skills & Early Years
Decision published: 13/09/2022
Effective from: 21/09/2022
Decision:
RESOLVED - That:
Permission is given to directly award a contract to:
1. Better Communication CIC to carry out research and evaluation to
produce thematic Early Years report.
2. Centre for Applied Education Research (CAER) to carry out
research and evaluation to produce thematic Mental Health
report
Lead officer: Sally Robson
08/09/2022 - Commissioning of contractor to produce Opportunity Area early years and mental health thematic evaluation report ref: 4497 Recommendations Approved
A decision is sought to request approval for
an exemption from the Contract Procedure Rules for a contract to be
awarded directly to:
1. Better Communication CIC to carry out research and evaluation to
produce thematic Early Years report.
2. Centre for Applied Education Research (CAER) to carry out
research and evaluation to produce thematic Mental Health
report
Decision Maker: Director of Education, Skills & Early Years
Decision published: 13/09/2022
Effective from: 21/09/2022
Decision:
RESOLVED - That:
an exemption be approved under Rule 21.3(i) of the Contract
Procedure Rules to directly award a contract to Better
Communication CIC and Centre for Applied Education Research (CAER)
to carry out research
and evaluation to produce thematic Early Years and Mental Health
reports.
Lead officer: Sally Robson
12/09/2022 - Delegated Officer Report - Award of Contract for the Provision of School Swimming Transport Services ref: 4499 Recommendations Approved
To award the contract for the provision of the
School Swimming Transport Services, after going through a full
tender process. This will ensure that a safe and high-quality
transport provision is provided to children in our borough so that
they can travel from their school to the swimming pool, and visa
versa to access the school swimming provision. The contract is for
3 years from September 2022 up to July 2025, with an option to
extend for a further two years. The level of transport provision
needed is dependant on the level of school buy backs in to the
service each year.
Decision Maker: Cabinet Member - Children and Young People and Deputy Leader
Decision published: 13/09/2022
Effective from: 21/09/2022
Decision:
RESOLVED - That:
To award and enter into the contract following the completion of
the tender evaluation process on behalf of the Council due to the
need to award the contract to allow sufficient time for
implementation of the provision and contract start date on week
commencing 12 September 2022.
Lead officer: Neil Consterdine