RESOLVED - That:
1. Using Cabinet Delegated Authority – increase budget
allowance to cover the site investigation costs in relation to the
PCSA award with Tilbury Douglas (TD) required to cover the
additional surveys and associated services and professional works
undertaken during the PCSA stage. Additional cost of
£34,603.26 excl. VAT – increasing the PCSA total to
£963,911.62 excl .VAT.
2. Using Cabinet Delegated Authority – increase budget
allowance in relation to the Enabling Works Contract award with
Tilbury Douglas (TD) required to cover the additional necessary
demolition and soft strip costs. Additional cost of
£143,794.44 excl. VAT.
3. Using Cabinet Delegated Authority – further increasing
budget allowance on enabling works contract by £1,336,522.75,
taking the enabling works contract to total value of
£3,822,786.74, to enable necessary additional asbestos
removal works to be undertaken early 2026 to facilitate the
refurbishment works of the Coliseum building.
4. Agreement to the award of £200,559.47 for RIBA Stage 5
Design Fees with Tilbury Douglas to undertake necessary design
works to the Coliseum building to facilitate completion date of the
Coliseum in 2026.