Creating a Better Place – Spindles Enabling Works 1 Variation 6b

16/03/2023 - Creating a Better Place – Spindles Enabling Works 1 Variation 6b

RESOLVED - That:
Option 1 – progress as set out within this report and uplift the value of Enabling Works 1 to enable Willmott Dixon to maintain programme and commence demolition of former TJ Hughes
Option 2 – Place the works on hold until Main Works contracts are in place for the Market, Events and Archive