Report of the Director of Adult Social Services
Additional documents:
Minutes:
The Cabinet considered a report of the Director of Adult Social Services (DASS) which advised that the Domestic Property Disability Adaptations (DPDA) Framework, which provided essential works such as Level Access Showers and Shower over Baths through the Disabled Facilities Grant (DFG), had exceeded its approved contract value and cannot be extended within the limits set by the Council’s Contract Procedure Rules. It was therefore proposed to end the framework following its current one-year extension, seek an exemption to regularise spend via a direct award, and secure continuity of service beyond November 2025.
The Council had a multi
contractor Framework Agreement in place for Domestic Property
Disability Adaptations (DPDA), which commenced on 1 December 2022
for an initial term of 2 years with the option to extend twice,
each for an additional term of no more than 1 year. Under the
Framework Agreement, the Council places orders for the provision of
Level Access Showers and Shower over Baths, as and when required.
The Framework Agreements were put in place to enable the Council to
meet its duty to award a Disabled Facility Grant (DFG) to those who
are eligible and to ensure the works funded by a DFG are completed
to a high standard and in a timely manner.
The initial 2-year term of the
Framework Agreement, which the Council has entered with each of the
4 appointed contractors, expired on 30th November 2024.
An extension was granted for 1 year and is due to expire on
30th November 2025, as outline in Appendix A. The
Framework Agreement provides that 28 days’ written notice is
required to be served on the Contractor to extend the initial
term.
The cost of the extended term
is not within the capped total life of contract costs set at
£2,260,000, as approved in the original Cabinet report for
the procurement of DPDA works requirements and as provided for in
the advertised opportunity. The spend to date is
£3,089,518.45, which exceeds both the original approval and
the maximum permitted modification under the Council’s
Contract Procedure Rules (CPRs).
Under the CPRs, a modification
of up to 15% (in this case, £339,000) would have been
permissible, resulting in a total of £2,599,000. As the
actual spend has already exceeded this figure, an exemption to the
CPRs is required. This report therefore seeks approval to end the
Framework Agreements and to formally request an exemption for a
direct award to regularise the position and enable continued
delivery of this essential service.
The DFG budget for this year is
£3,044,703.82. The spend to date from the DFG budget is
£1,034,003.19 which leaves an outstanding budget of
£2,010,700.63. Projected spend to the end of the framework
will also need to be calculated to ensure it remains within the
wider thresholds.
The report also sought approval to increase the framework prices by 5% from April 2025 to November 2025. And to ensure the uplift it in the direct award for December 2025 to November 2026.
Options/Alternatives considered:
Option 1: ... view the full minutes text for item 12