Decision Maker: Director of Environment
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
This report seeks delegated approval of:
•The Appointment of the Contractor for the proposed works on
Rock St as Part of The Mayors Challenge Fund (MCF) utilising the
Accessible Oldham Strategic Partner Agreement (AOSPA)
Framework.
RESOLVED - That:
to award the call off contract, to the value of £1,286,649,
utilising delegated approval at director level which was approved
by Cabinet
Option 1 - Award the call off contract through
the AOSPA framework to Rowan Ashworth Ltd
Option 2 - Do not award the call off contract. The works will not
be carried out using this contract and risk delays to the delivery
programme for this and subsequent schemes.
Option 2
Other reasons / organisations consulted
Not applicable
Contact: Jeannette Whitney, Technical Support Admin Email: naz.huda@oldham.gov.uk Email: jeanette.whitney@oldham.gov.uk.
Publication date: 13/09/2023
Date of decision: 06/09/2023
Effective from: 21/09/2023
Accompanying Documents: