Decision Maker: Director of Economy
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
This report requests approval to modify
Construction and Highways Works
RESOLVED - That:
To allow service continuity it is approved that the Framework
Agreements in place with contractors appointed to those 13 x lots
identified in this report are modified to allow an uplift to each
contractor’s Schedule of Rates in line with BCIS index at
12.66% for the period 3rd October 2022 to 2nd October 2023
Option 1 - To allow service continuity it is
recommended that the Framework Agreements in place with contractors
appointed to those 13 x lots identified in this report are modified
to allow an uplift in line with BCIS index at 12.66% for the period
3rd October 2022 to 2nd October 2023.
Option 2 - To cease to call-off works under the framework
agreements (where contractors refuse to quote on existing rates)
and to revert to obtaining quotations and tenders for all work
packages to comply with the Council’s Contract Procedure
Rules, which would be an inefficient, labour and time-consuming
process. It is also considered unlikely that alternative
contractors could be sourced to provide the services.
Option 2 - To cease to call-off works under
the framework agreements (where contractors refuse to quote on
existing rates) and to revert to obtaining quotations and tenders
for all work packages to comply with the Council’s Contract
Procedure Rules, which would be an inefficient, labour and
time-consuming process. It is also considered unlikely that
alternative contractors could be sourced to provide the
services.
Other reasons / organisations consulted
consultation held between Legal, Procurement
and Property teams to evaluate and review contractual position and
explore options to continue service deilivery
Contact: John Winterbottom, Divisional manager - Technical Delivery Email: john.winterbottom@oldham.gov.uk Email: john.winterbottom@oldham.gov.uk.
Publication date: 17/01/2023
Date of decision: 15/12/2022