Decision Maker: Cabinet Member - Neighbourhoods
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Working involving the replacement of a
dilapidated masonry culvert.
Approval is sought to appoint Rowan Ashworth
Limited, who submitted the most economically advantageous and
methodologically sound tender, to commence the reconstruction of
the Thurston Clough Culvert and associated structures located at
Thurston Clough Road in Delph
Option 1 is to reconstruct the existing
dangerously dilapidated structure known as BR430 Thurston Clough
Culvert and associated structures. This option delivers a permanent
solution and will allow the adopted public highway above the
structure to be reopened on completion using the least amount of
capital expenditure.
Option 2 is to retain the existing vehicular road closure of
Thurston Clough Road and monitor the structure(s) for further signs
of movement. This option exposes the Council to the risk of
catastrophic collapse of the structure(s) and could result in loss
of life, damage to the adjacent residential private property and
destruction of several underground services that are present above
the existing culvert structure. This scenario would inevitably
result in additional costs to the Council and may also result in
the extent of the permanent works being increased which would,
therefore, escalate the costs of said permanent works.
Option 2
Reason Key: Expenditure > £250,000 (Significant expenditure or savings);
Wards Affected: Saddleworth North;
Key Decision Reference: NEI-16-19
Making Representations: N/A
Other reasons / organisations consulted
Consultation with ward members prior to
starting on site.
Consultees
Ward members.
Contact: Rezwan Khan, Senior Engineer Rezwan Khan Email: rezwan.khan@unitypartnership.com.
Publication date: 08/01/2020
Date of decision: 18/12/2019
Effective from: 16/01/2020