Decision Maker: Director of Communities
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
This report seeks the following
authorisations:
To seek approval to amend existing lease agreements for the A Bed
Every Night (ABEN) accommodation portfolio to ensure continued
compliance with GMCA grant conditions and to support the effective
operation, management, and maintenance of leased properties over
the remaining 2.5 year funding period.
A) Approve the amendments to the existing ABEN lease agreements in
line with the proposed wording in Appendix A, ensuring continued
compliance, clarity of responsibilities, and effective service
operation.
B) Approve the granting of:
•a 12 month lease for 10 Sharples Hall Street -18 bed unit
total annual rent: £108,000
•a 12 month lease for 20 Vicarage Street- 6 bed unit- total
annual rent: £33,336
RESOLVED - That:
A) Approve the amendments to the existing ABEN lease agreements in
line with the proposed wording in Appendix A, ensuring continued
compliance, clarity of responsibilities, and effective service
operation.
B) Approve the granting of:
•a 12 month lease for 10 Sharples Hall Street
•a 12 month lease for 20 Vicarage Street
both of which support service continuity and provide flexibility in
line with the 2.5 year GMCA funding period.
These leases retain the existing 4 week termination clause, meaning
no additional risk to the local authority.
Option 1 -
Approve Recommended Actions (Recommended)
A) Approve the amendments to the existing ABEN lease agreements in
line with the proposed wording in Appendix A, ensuring continued
compliance, clarity of responsibilities, and effective service
operation.
B) Approve the granting of:
•a 12 month lease for 10 Sharples Hall Street
•a 12 month lease for 20 Vicarage Street
both of which support service continuity and provide flexibility in
line with the 2.5 year GMCA funding period.
These leases retain the existing 4 week termination clause, meaning
no additional risk to the local authority.
Option 2 -
End Current Leases and Seek Alternative Provision (Not
Recommended)
Terminate the existing leases and attempt to source new
accommodation. This option is not recommended because:
•Suitable alternative accommodation is unlikely to be found at
a lower cost than the favourable rent already negotiated with
current landlords.
•The process would result in significant operational
disruption, including decanting residents and establishing new
placements.
•There would be an increased risk of service interruption,
loss of ABEN bed capacity, and a potential impact on GMCA grant
funding.
•There is a high likelihood of cost escalation, delays in
reopening the service, and challenges in maintaining statutory
compliance during transition
Option 3 -
Continue operating under the existing lease arrangements without
amendment. This option is not recommended, as it would:
•Leave unresolved issues around responsibilities for repairs,
compliance checks, and defect reporting.
•Continue to expose the service to operational delays,
ambiguity, and compliance risks.
•Not provide the clarity required to support effective
partnership working with the landlord and managing agent
Option 2 -
End Current Leases and Seek Alternative Provision (Not
Recommended)
Terminate the existing leases and attempt to source new
accommodation. This option is not recommended because:
•Suitable alternative accommodation is unlikely to be found at
a lower cost than the favourable rent already negotiated with
current landlords.
•The process would result in significant operational
disruption, including decanting residents and establishing new
placements.
•There would be an increased risk of service interruption,
loss of ABEN bed capacity, and a potential impact on GMCA grant
funding.
•There is a high likelihood of cost escalation, delays in
reopening the service, and challenges in maintaining statutory
compliance during transition
Option 3 -
Continue operating under the existing lease arrangements without
amendment. This option is not recommended, as it would:
•Leave unresolved issues around responsibilities for repairs,
compliance checks, and defect reporting.
•Continue to expose the service to operational delays,
ambiguity, and compliance risks.
•Not provide the clarity required to support effective
partnership working with the landlord and managing agent
Other reasons / organisations consulted
None to declare
Contact: Clare Ocansey, Tenancy Relations Officer Email: clare.ocansey@oldham.gov.uk Email: Clare.Ocansey@oldham.gov.uk.
Publication date: 13/05/2026
Date of decision: 06/05/2026
Accompanying Documents: