Decision Maker: Director of Communities, Director of Environment
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
In light of recent developments relating to
the funding announcement from Greater Manchester Combined Authority
(GMCA), Oldham Council is poised to further its commitment to the A
Bed Every Night initiative in collaboration with the GMCA.
On the 27th of March 2025, the council received confirmation of
£391,248 funding from GMCA, enabling the ABEN Service to
extend its reach until the 30th of September 2029, encompassing an
additional four bedspaces.
RESOLVED - That:
1. To authorise an exemption under rule 21 of the Council’s
Contract Procedure Rules (CPRs) in respect of the procurement
procedures which must be followed under rule 4 of the CPRs, based
on contract value.
2. To approve a direct award of a contract for the ABEN Phase 5
year 4, which would commence on the 1st of April 2026 and expire on
30th September 2026. The total contract fee payable to DePaul would
be £122,500 (VAT Exempt).
3. It is noted that the funding award will cover a 2.5 year
period.
4. That the current contract be extended for an additional 6 months
to allow sufficient time to complete full procurement
activities.
Option 1 - To approve an exemption in respect
of rule 4 of the Contract Procurement Rules by utilising rule 21 of
the CPRs, and
Option 2: Do not approve the proposed exemption under rule 21 of
the CPRs, end the external delivery of the ABEN Service and deliver
the service in-house.
Option 3: Do Nothing. Ceasing to deliver ABEN would cause
reputational damage to the Council and increase rough sleeping in
the Borough, which would also go against the Council’s own
Ending Rough Sleeping Plan and directives from MHCLG.
.
Options 2 and 3
Other reasons / organisations consulted
None
Contact: Seyi Adeyemi, Senior Housing Needs Officer Email: seyi.adeymi@oldham.gov.uk Email: seyi.adeyemi@oldham.gov.uk.
Publication date: 01/05/2026
Date of decision: 17/04/2026
Accompanying Documents: