Decision Maker: Leader of the Council and Cabinet Member for Growth
Decision status: Recommendations Approved (subject to call-in)
Is Key decision?: No
Is subject to call in?: Yes
Requirement to increase value of the approved
PCSA value, amend enabling works contract with Tilbury Douglas to
undertake further works and asbestos removal works within the
building and approval of RIBA Stage 5 Design fees to facilitate the
refurbishment works of the Coliseum building.
RESOLVED - That:
1. Using Cabinet Delegated Authority – increase budget
allowance to cover the site investigation costs in relation to the
PCSA award with Tilbury Douglas (TD) required to cover the
additional surveys and associated services and professional works
undertaken during the PCSA stage. Additional cost of
£34,603.26 excl. VAT – increasing the PCSA total to
£963,911.62 excl .VAT.
2. Using Cabinet Delegated Authority – increase budget
allowance in relation to the Enabling Works Contract award with
Tilbury Douglas (TD) required to cover the additional necessary
demolition and soft strip costs. Additional cost of
£143,794.44 excl. VAT.
3. Using Cabinet Delegated Authority – further increasing
budget allowance on enabling works contract by £1,336,522.75,
taking the enabling works contract to total value of
£3,822,786.74, to enable necessary additional asbestos
removal works to be undertaken early 2026 to facilitate the
refurbishment works of the Coliseum building.
4. Agreement to the award of £200,559.47 for RIBA Stage 5
Design Fees with Tilbury Douglas to undertake necessary design
works to the Coliseum building to facilitate completion date of the
Coliseum in 2026.
Option 1 - • Do not carry out the
additional surveys.
This would result in unknown elements and risk being incorporated
into the main contract award, thereby increasing possibility of
increased costs and delays to the refurbishment works.
Option 2 - • Do not amend the enabling works contract.
This would result in these works being delayed until the main
contract award – this would delay works on the building. This
option would delay the re-opening of the Coliseum theatre and
potentially increase costs.
Option 3 -• Do not instruct RIBA Stage 5 Design Fees
This would result in these works being delayed until the main
contract award – this would delay works on the building. This
option would delay the re-opening of the Coliseum theatre and
potentially increase costs.
Option 4 - approval.
Option 1 - • Do not carry out the
additional surveys.
This would result in unknown elements and risk being incorporated
into the main contract award, thereby increasing possibility of
increased costs and delays to the refurbishment works.
Option 2 - • Do not amend the enabling works contract.
This would result in these works being delayed until the main
contract award – this would delay works on the building. This
option would delay the re-opening of the Coliseum theatre and
potentially increase costs.
Option 3 -• Do not instruct RIBA Stage 5 Design Fees
This would result in these works being delayed until the main
contract award – this would delay works on the building. This
option would delay the re-opening of the Coliseum theatre and
potentially increase costs.
Other reasons / organisations consulted
None
Contact: Ian Foy, Team Leader Project Management, Building & Quantity Surveyors Email: ian.foy@oldham.gov.uk Email: Ian.Foy@Oldham.gov.uk.
Publication date: 10/12/2025
Date of decision: 08/12/2025
Date comes into force if not called in: 25/12/2025
Call-in deadline date: 24/12/2025
Current call-in Count: 0