Decision Maker: Director of Economy
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To request the approval of an exemption under
rule 21 of Contract Procedure Rules (CPRs) in respect of the
obligation under rule 4 of the CPRs to comply with the prescribed
procurement procedure for a works contract with a value of
£84,994.47.
RESOLVED - That:
Part A
In accordance with rule 21.3 of the Contract Procedure Rules,
approve:
An exemption to the procurement procedures prescribed under rule 4
of the Contract Procedure Rules to allow for a direct contract
award without competition to be made to Seddon Construction to
deliver the works detailed in this report.
Part B
Subject to the approval of the requested exemption under Part
A,
1. To directly appoint and to enter into a contract with Seddon
Construction to the value of £84,994.47 excluding VAT.
2. Approve the budget required for the proposed works from within
the School Condition Allowance allocation
3. Approve the appointment of Seddon Construction and authorise the
finalisation of the published form of contract so that the Council
can enter into a Contract with Seddon Construction for the tendered
works.
4. Delegate authority to the Borough Solicitor to carry out all
necessary legal formalities.
Option 1 - Direct appoint Seddon Construction
along with their appointment under the form of contract.
Option 2 - Tender the works competitively and launch a mini
competition. This is not considered a viable option, as this will
add a number of weeks onto the programme and make hitting the
October half term target extremely difficult. The school has also
been identified by the Property team as a high risk of failure of
the boiler plant, which could lead to the school closing if not
replaced.
Option 2 - Tender the works competitively and
launch a mini competition. This is not considered a viable option,
as this will add a number of weeks onto the programme and make
hitting the October half term target extremely difficult. The
school has also been identified by the Property team as a high risk
of failure of the boiler plant, which could lead to the school
closing if not replaced.
Other reasons / organisations consulted
None
Contact: Ian Foy, Team Leader Project Management, Building & Quantity Surveyors Email: ian.foy@oldham.gov.uk Email: Ian.Foy@Oldham.gov.uk.
Publication date: 17/12/2025
Date of decision: 08/10/2025