Decision details

Exemption from Contract Procedure Rules – Crompton School Boiler Replacement

Decision Maker: Director of Economy

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To request the approval of an exemption under rule 21 of Contract Procedure Rules (CPRs) in respect of the obligation under rule 4 of the CPRs to comply with the prescribed procurement procedure for a works contract with a value of £84,994.47.

Decision:

RESOLVED - That:
Part A
In accordance with rule 21.3 of the Contract Procedure Rules, approve:
An exemption to the procurement procedures prescribed under rule 4 of the Contract Procedure Rules to allow for a direct contract award without competition to be made to Seddon Construction to deliver the works detailed in this report.

Part B
Subject to the approval of the requested exemption under Part A,
1. To directly appoint and to enter into a contract with Seddon Construction to the value of £84,994.47 excluding VAT.
2. Approve the budget required for the proposed works from within the School Condition Allowance allocation
3. Approve the appointment of Seddon Construction and authorise the finalisation of the published form of contract so that the Council can enter into a Contract with Seddon Construction for the tendered works.
4. Delegate authority to the Borough Solicitor to carry out all necessary legal formalities.

Reasons for the decision:

Option 1 - Direct appoint Seddon Construction along with their appointment under the form of contract.
Option 2 - Tender the works competitively and launch a mini competition. This is not considered a viable option, as this will add a number of weeks onto the programme and make hitting the October half term target extremely difficult. The school has also been identified by the Property team as a high risk of failure of the boiler plant, which could lead to the school closing if not replaced.

Alternative options considered:

Option 2 - Tender the works competitively and launch a mini competition. This is not considered a viable option, as this will add a number of weeks onto the programme and make hitting the October half term target extremely difficult. The school has also been identified by the Property team as a high risk of failure of the boiler plant, which could lead to the school closing if not replaced.

Other reasons / organisations consulted

None

Contact: Ian Foy, Team Leader Project Management, Building & Quantity Surveyors Email: ian.foy@oldham.gov.uk Email: Ian.Foy@Oldham.gov.uk.

Publication date: 17/12/2025

Date of decision: 08/10/2025