Decision Maker: Deputy Chief Executive -
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Part A: Requirement for an exemption under
rule 21.3 (j) of the Contract Procedure Rules (CPRs) to waive the
procurement procedures under rule 4 of the CPRs, which would enable
a direct award of a contract to be considered under Part B.
Part B: Subject to approval of the proposed exemption under Part A,
appoint E.On Control Solutions Ltd. to provide Maintenance of
Building Energy Management Systems (BEMS)on Council assets for a
period of 12 months.
RESOLVED - That:
Part A
In accordance with rule 21.3 (j) of the Contract Procedure Rules,
approve:
An exemption to the procurement procedures prescribed under rule 4
of the Contract Procedure Rules to allow for a direct contract
award without competition to be made to E.On Control Solutions Ltd.
to deliver those services detailed in this report.
21.3(j) Where continued provision of Supplies, Works or Services is
required for an additional period and this can be justified, for
example where a service review includes the intention to
co-terminate relevant Contracts within a reasonable period with all
exceptional circumstances to be objectively evidenced in the
exemption request to enable the decision maker to reach an informed
and reasonable decision in the circumstances.
Part B
Subject to the approval of the requested exemption under Part
A,
1.
To directly appoint and to enter into a contract with E.On Control
Solutions Ltd. for a period of 12 months for Maintenance of
Building Energy Management Systems (BEMS)on Council assets with a
maximum contract value of £50,000.
2.
Approve the budget required for the proposed 12-month period
3.
Approve the appointment of E.On Control Solutions Ltd. and
authorise the completion of necessary contract documentation, so
that the Council can enter into a Contract with E.On Control
Solutions Ltd. for the proposed Contract.
4.
Delegate authority to the Borough Solicitor to carry out all
necessary legal formalities.
Not to allow interim contracts. This would put
the Council at greater risk with contractors not having surety of
contract and set contract terms.
None
Other reasons / organisations consulted
None
Contact: Ian Foy, Team Leader Project Management, Building & Quantity Surveyors Email: ian.foy@oldham.gov.uk Email: Ian.Foy@Oldham.gov.uk.
Publication date: 26/09/2025
Date of decision: 01/09/2025