Decision Maker: Deputy Chief Executive -
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To appoint and enter into a contract with Buro
Happold to carry out Commercialisation feasibility work for the
Oldham Low Carbon Heat Network project.
RESOLVED - That:
Appoint and enter into a contract with Buro Happold. Under this
option, Buro Happold will proceed to complete the Commercialisation
feasibility work for the Oldham Low Carbon Heat Network for
inclusion in the procurement of the Oldham Green New Deal Delivery
Partner.
Option 1 – Do not appoint and enter into
a contract with Buro Happold. Under this option, the Oldham Low
Carbon Heat Network project will not proceed and the Council will
surrender the Green Heat Network Fund grant which has been secured
for this work. The Oldham Low Carbon Heat Network will not be the
Anchor Project in the procurement of the Oldham Green New Deal
Delivery Partner.
Option 2 – Appoint and enter into a contract with Buro
Happold. Under this option, Buro Happold will proceed to complete
the Commercialisation feasibility work for the Oldham Low Carbon
Heat Network for inclusion in the procurement of the Oldham Green
New Deal Delivery Partner.
Option 1 – Do not appoint and enter into
a contract with Buro Happold. Under this option, the Oldham Low
Carbon Heat Network project will not proceed and the Council will
surrender the Green Heat Network Fund grant which has been secured
for this work. The Oldham Low Carbon Heat Network will not be the
Anchor Project in the procurement of the Oldham Green New Deal
Delivery Partner.
Other reasons / organisations consulted
None.
Contact: Andrew Hunt, Strategy Partnerships and Policy Manager Email: andrew.hunt@oldham.gov.uk Email: andrew.hunt@oldham.gov.uk.
Publication date: 02/08/2024
Date of decision: 31/07/2024
Accompanying Documents: