Decision Maker: Deputy Chief Executive -
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
As part of the CRSTS (City Regional
Sustainable Transport Settlement) funding, Oldham Council Highways
devise a data led approach to deliver a carriageway maintenance
programme. As part of that programme development for 2024/25, a
number of roads have been prioritised to utilise the funding in
full. One of these schemes is Burnley Lane, Chadderton (from Elk
Mill Roundabout through to Junction with Mill Brow).
RESOLVED - That:
Option 1 is recommended; to progress the resurfacing of Burnley
Lane for early delivery, and works begin on site as soon as
possible to bring the carriageway up to standard
Option 1 - The proposed resurfacing of Burnley
Lane is approved for early delivery and works begin on site as soon
as possible to bring the carriageway up to standard.
Option 2 - The proposed resurfacing of Burnley Lane is not approved
for early delivery, and the road is patched at a cost of
£14,162 (and additional monthly costs) until Burnley Lane is
resurfaced later in 2024/25
Option 2
Other reasons / organisations consulted
Not applicable
Contact: Gordon Anderson, Head of Highways & Engineering - Unity Partnership Email: gordon.anderson@oldham.gov.uk Email: Gordon.Anderson@oldham.gov.uk.
Publication date: 17/04/2024
Date of decision: 09/04/2024
Accompanying Documents: