Decision Maker: Director of Economy
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To confirm RIBA Stage 2 design sign off and to proceed to Stage 3 plus design. Instruction for Enabling Works Phase 1, as highlighted at Option 1 below.
RESOLVED - That:
Enabling works and stage 3 design should proceed.
Option 1 - Option 1 is to instruct on a Phase
1 enabling works package. The reason for this recommendation is to
avoid the potential for a delay to the programme caused by the bird
nesting season which starts in March; support the completion of all
pre-construction design stages, deliver a final price for the main
contract, secure planning consent and stay on programme to stay
within budget and meet external funders programme timescales.
Option 2 is to choose to not start the enabling works package. This
would delay the main contract start by 2 months, require the
enabling works to be subsumed into an extended programme main
contract and result in a higher final price from the contractor.
Importantly the enabling works package is critical if the Council
want WDC to provide a final price for the main contract.
Option 2 is to choose to not start the
enabling works package. This would delay the main contract start by
2 months, require the enabling works to be subsumed into an
extended programme main contract and result in a higher final price
from the contractor. Importantly the enabling works package is
critical if the Council want WDC to provide a final price for the
main contract.
Other reasons / organisations consulted
N/A
Contact: Andrew Hall, Principal Regeneration Officer Email: andrew.hall@oldham.gov.uk Email: andrew.hall@oldham.gov.uk.
Publication date: 26/02/2024
Date of decision: 31/01/2024