Decision details

Northern Roots – Visitor Centre and External Works; Learning Centre.

Decision Maker: Executive Director for Place & Economic Growth

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: No

Purpose:

To appoint a construction contractor under a Pre-Construction Services Agreement (PCSA) for the construction of a Visitor Centre and a Learning Centre on the North Roots site. To appoint the client-side consultant team for RIBA Stages 4 to 7.

Decision:

RESOLVED - That:
Option 1 - Implement the outcome of the first stage tender process to appoint the preferred contractor to progress the project on the Northern Roots site to the next stage. Appoint the client team to support the pre-construction and construction phases of this project.

Reasons for the decision:

Option 1 - Award Contract
Option 2 – Do not implement the outcome of the first stage tender process.

Alternative options considered:

Option 2 – Do not implement the outcome of the first stage tender process.

Other reasons / organisations consulted

Ward Councillors were consulted. officers consulted

Contact: Andrew Hall, Principal Regeneration Officer Email: andrew.hall@oldham.gov.uk Email: andrew.hall@oldham.gov.uk.

Publication date: 12/09/2023

Date of decision: 26/08/2023