Decision Maker: Executive Director for Place & Economic Growth
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To seek approval for exemption from CPR with
the aim to deliver a specialist scheme of works on the Pennine Way
by CPY Excavations
RESOLVED - That:
Exempt Contract Procedure Rules and approve the direct award of a
contract to CPY Excavations - Due to the time restraints and
required specialist knowledge and operations it is recommended to
proceed with CPY Excavations as the designated contractor with a
proven history of similar schemes
Undertake an open quotation process in
accordance with Contract Procedure Rules - Due to the time
restraints and required specialist knowledge and operations it is
highly unlikely to source an alternative contractor with the
necessary knowledge and experience of delivering this scheme.
Not applicable
Other reasons / organisations consulted
Not applicable
Contact: Liam Kennedy, PRoW Officer Email: liam.kennedy@oldham.gov.uk Email: Liam.Kennedy@unitypartnership.com.
Publication date: 13/09/2023
Date of decision: 22/08/2023
Accompanying Documents: