Decision Maker: Cabinet Member - Culture and Leisure, Cabinet Member - Finance, Corporate Services and Sustainability and Deputy Leader, Leader of the Council and Cabinet Member for Growth, Chief Executive, Director of Finance, Director of Legal (Monitoring Officer), Executive Director Place (Deputy Chief Executive)
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
In February 2022 Cabinet approved a
Pre-Construction Services Agreement (PCSA) contract to be entered
into
On 25th July Cabinet gave approval to split workstreams for the
Spindles Redevelopment into Project 1 (demolition of TJ Hughes,
construction of a new market and events space and works to the
roof) and Project 2 (redevelopment of internal retail units to
create workspace).
As a result of this, an instruction is required for the Stage 5
design fees
RESOLVED - That:
Option 1 is recommended to allow the programme to progress in line
with current agreed programme dates.
Option 1 – progress as set out within
this report and uplift the value of PCSA to enable Willmott Dixon
to maintain programme and progress the Stage 5 design
Option 2 – Place the works on hold until Main Works contracts
are in place for the Market, Events and Archive
Option 2.
Other reasons / organisations consulted
N/A
Contact: Paul Clifford, Director of Economy Email: paul.clifford@oldham.gov.uk Email: paul.clifford@oldham.gov.uk.
Publication date: 26/04/2023
Date of decision: 12/04/2023
Effective from: 13/05/2023