Decision Maker: Executive Director for Place & Economic Growth
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
This report seeks delegated approval of:
•The award of Accessible Oldham – A62 Bridges
Refurbishment Works Call Off Order;
•The approval of the appointment of the Contractor for the
works.
RESOLVED - That:
Delegated approval for the A62 Bridges Refurbishment Works is
accepted and that the Call Off Order and Contract for the works are
awarded to Rowan Ashworth Ltd, the Council’s Strategic
Partner
Option 1 - Delegated approval for the A62
Bridges Refurbishment Works is accepted and that the Call Off Order
and Contract for the works are awarded to Rowan Ashworth Ltd, the
Council’s Strategic Partner
Option 2 - Use a competitive tender process to appoint a
Contractor. This is a lengthy process that will result in
significant programme delays
Option 2
Other reasons / organisations consulted
Not applicable
Contact: Rezwan Khan, Senior Engineer Email: rez.khan@oldham.gov.uk Email: rezwan.khan@unitypartnership.com.
Publication date: 08/12/2022
Date of decision: 29/11/2022