Decision Maker: Leader of the Council and Portfolio Holder for Reform and Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
Oldham Council’s A Bed Every Night
(ABEN) rough sleepers’ accommodation project requires
recommissioning from 1st July 2022 in line with contract procedure
rules. This is scheduled before Cabinet on 20th June 2022, seeking
delegated approval for the Cabinet Member for Housing to award the
contract to the successful bidder following a competitive tendering
process.
Due to the required standstill period following contract award,
this report seeks approval to extend the current ABEN Phase 4
contract to the 17th July, with Phase 5 commencing from 18th
July.
RESOLVED - That:
Agree to issue the ABEN contract extension to 17th July, with an
option to extend up to 3 months if required
1.(Recommended) Agree to issue the ABEN
contract extension to 17th July, with an option to extend up to 3
months if required
2.(Not recommended) Not issue the contract extension: This could
risk ceasing support provision in ABEN, which would be at a
detriment to residents and be contrary to the grant agreement with
GMCA
3.(Not recommended) Deliver in-house: It is unlikely that the
Council could recruit and train new staff in time to deliver ABEN,
and there is no capacity to do so within existing resources. It is
therefore not recommended that this option is pursued.
2.(Not recommended) Not issue the contract
extension: This could risk ceasing support provision in ABEN, which
would be at a detriment to residents and be contrary to the grant
agreement with GMCA
3.(Not recommended) Deliver in-house: It is unlikely that the
Council could recruit and train new staff in time to deliver ABEN,
and there is no capacity to do so within existing resources. It is
therefore not recommended that this option is pursued.
Other reasons / organisations consulted
Cabinet Member has been briefed on ABEN and is
supportive of the decision to move forward.
Contact: Fiona Carr, Principal Homelessness Strategy Officer Email: fiona.carr@oldham.gov.uk Email: fiona.carr@oldham.gov.uk.
Publication date: 29/06/2022
Date of decision: 20/06/2022
Effective from: 07/07/2022
Accompanying Documents: