Decision details

Old Library Refurbishment Contract Modification

Decision Maker: Leader of the Council and Portfolio Holder for Reform and Regeneration

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To seek approval to issue a Main Works contract modification to Tilbury Douglas Construction to increase the scope of Phase 1 priority works at the Old Library on Union Street.

Decision:

RESOLVED - That:
Option 1: proceed with a Phase 1 contract modification
A contract modification would facilitate a process that targets best value for the Council and opportunities to access time and cost benefits of a fully integrated development programme.

Reasons for the decision:

Option 1: Proceed with a phase 1 contract modification
Option 2: Do not proceed with a phase 1 contract modification

Alternative options considered:

Option 2 has been rejected

Other reasons / organisations consulted

Relevant Council departments have been consulted including:
Finance
Procurement
Legal
Property

Contact: Nigel Fraser, Principal Regeneration Oficer Email: nigel.fraser@oldham.gov.uk Email: nigel.fraser@oldham.gov.uk.

Publication date: 27/05/2022

Date of decision: 23/05/2022

Effective from: 04/06/2022