The purpose of the report is to obtain approval to lease to ENWL a new substation at Alexandra Park, Oldham

Decision:

RESOLVED - That: The lease of a new substation to ENWL is approved.

Reasons for the decision:

Option 1 - Not to progress this letting.
Option 2 - Progress the letting as described in this report which will accelerate the regeneration of Alexandra Park.

Alternative options considered:

Option 1

Other reasons / organisations consulted

Colleagues in legal, and finance have been consulted.