Decision Maker: Executive Director for Place & Economic Growth
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The purpose of the report is to obtain
approval to lease to ENWL a new substation at Alexandra Park,
Oldham
RESOLVED - That: The lease of a new substation
to ENWL is approved.
Option 1 - Not to progress this letting.
Option 2 - Progress the letting as described in this report which
will accelerate the regeneration of Alexandra Park.
Option 1
Other reasons / organisations consulted
Colleagues in legal, and finance have been
consulted.
Contact: Brian Enright, Principal Regeneration Officer Email: brian.enright@oldham.gov.uk Email: brian.enright@oldham.gov.uk.
Publication date: 29/09/2021
Date of decision: 28/09/2021
Accompanying Documents: