Decision Maker: Cabinet Member - Education and Skills
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
A decision is needed for Kier Construction
Northern ltd to complete enabling works ahead of the main works for
the expansion of North Chadderton school starting.
RESOLVED - That:
Option 1 – Agree the enabling works for the reasons set out
in this report.
Option 1 – Agree the enabling works for
the reasons set out in this report.
Option 2 – Do not agree the enabling works, which would cause
additional disruption to the school, extend the programme beyond
September 2022.
Option 2 – Do not agree the enabling
works, which would cause additional disruption to the school,
extend the programme beyond September 2022.
Key Decision Reference: ED-03-21
Other reasons / organisations consulted
N/A
Contact: Andrew Hall, Principal Regeneration Officer Email: Andrew.hall@oldham.gov.uk Email: andrew.hall@oldham.gov.uk.
Publication date: 13/07/2021
Date of decision: 05/07/2021
Effective from: 21/07/2021
Accompanying Documents: