1.1Funding for the GM CAZ Service Agreement has been secured via the initial tranche of £36m of funding awarded by Government and written commitment from the Government’s Joint Air Quality Unit (JAQU) to provide the required additional £12.1m with risk and contingency being drawn down on an as needed basis. This funding will cover the GM CAZ Service supplier costs, the TfGM and Local Authority costs and other ‘third party’ costs required to successfully deliver the GM CAZ Service element of the GM Clean Air Zone. JAQU have been kept up to date with procurement activity and they are aware of GM’s intention to enter into contract with Egis Projects SA.
1.2In regards of operational costs, it is expected that revenue generated from the daily charges and penalty notices will cover all the operational costs. If the CAZ revenues are not sufficient over the life of the CAZ to cover the operational costs, as agreed with JAQU, the New Burdens Doctrine would cover any net deficit.

Decision:

RESOLVED - That: GMCA (acting by its officer, TfGM) is authorised to award the GM CAZ Services contact to Egis Projects SA, and as required by JAQU in support of the main contract enter into the contracts with KADOE (DVLA), Gov.UK.Pay, Stripe, Go-Cardless, PATROL for the Traffic Penalty Tribunal and with the Ministry of Justice for the Traffic Enforcement Centre.

Reasons for the decision:

Option 1 - To award the GM CAZ Services contact to Egis Projects SA, and as required by JAQU in support of the main contract enter into the contracts with KADOE (DVLA), Gov.UK.Pay, Stripe, Go-Cardless, PATROL for the Traffic Penalty Tribunal and with the Ministry of Justice for the Traffic Enforcement Centre.
Option 2 - Not to award the GM CAZ Services contact to Egis Projects SA, and as required by JAQU in support of the main contract enter into the contracts with KADOE (DVLA), Gov.UK.Pay, Stripe, Go-Cardless, PATROL for the Traffic Penalty Tribunal and with the Ministry of Justice for the Traffic Enforcement Centre.

Alternative options considered:

2

Other reasons / organisations consulted

Greater Manchester Local Authorities
Cabinet Members

Contact: Carol Brown, Assistant Executive Director - Environment Email: carol.brown@oldham.gov.uk Email: Carol.Brown@oldham.gov.uk.

Publication date: 20/07/2021

Date of decision: 07/07/2021

Effective from: 29/07/2021