Decision details

Signalisation of the Lees Road/Breeze Hill Road/ Wellyhole Street junction with associated improvements and crossing facilities as set out in a planning condition as part of the approval of PA/342585/18 – Erection of new secondary school (Oasis Leesb

Decision Maker: Cabinet Member - Neighbourhoods

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

The above works have been designed by the Unity Partnership Highways Team. The works will be delivered by the Council’s Highways Operations Team and will exceed £250,000. The highway works are the subject of a S278 agreement between Oldham Council and the Department for Education (DfE), due to be signed imminently, and will be fully funded by the DfE, half the costs when the agreement is signed and half on completion of the works, so in the interim period the costs will be incurred by the Council.

Decision:

RESOLVED - That:
Enter into the legal agreement with the DfE, receive half of the scheme funding on doing so, deliver the highway scheme over the summer months of 2021 and incur costs up to completion of the scheme, whereby the remaining costs will be claimed back from the DfE. This option fulfils the planning condition outlined above as part of the original planning approval.

Reasons for the decision:

Option 1 – enter into the legal agreement with the DfE, receive half of the scheme funding on doing so, deliver the highway scheme over the summer months of 2021 and incur costs up to completion of the scheme, whereby the remaining costs will be claimed back from the DfE. This option fulfils the planning condition outlined above as part of the original planning approval.
Option 2 – do not enter into the legal agreement with the DfE or deliver the highway scheme, thereby not fulfilling the planning condition outlined above.

Alternative options considered:

Option 2 – do not enter into the legal agreement with the DfE or deliver the highway scheme, thereby not fulfilling the planning condition outlined above.

Other reasons / organisations consulted

Oldham Council Officers
Unity Partnership Officers
Department for Education
Portfolio Holder

Contact: Eleanor Sykes, Transportation Policy Officer Email: eleanor.sykes@oldham.gov.uk Email: Eleanor.sykes@oldham.gov.uk.

Publication date: 02/06/2021

Date of decision: 02/06/2021

Effective from: 10/06/2021

Accompanying Documents: