This report seeks delegated approval of:
•The cost of micro surfacing Greengate
•The approval of the appointment of the contractor for the
works
Decision:
RESOLVED - That:
the delegated approval for these works is accepted and that the
contract for the works are awarded to Kier Highways Ltd
Reasons for the decision:
Option 1 - Approve the tender award to Kier
Highways Ltd for the micro surfacing of Greengate in line with
Oldham Council’s Contract Procedure Rules
Option 2 - Do not approve the tender award to Kier Highways Ltd for
the micro surfacing of Greengate, in line with Oldham
Council’s Contract Procedure Rules
Alternative options considered:
Option 2
Other reasons / organisations consulted
Not applicable
Contact: Matthew McGreal, Assistant Engineer Email: matt.mcgreal@unitypartnership.com Email: Matthew.McGreal@unitypartnership.com.
Publication date: 20/01/2021
Date of decision: 19/01/2021
Effective from: 28/01/2021