Decision Maker: Deputy Chief Executive -
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
In March 2020 Japanese Knotweed Control (JKC)
were appointed to remove the Japanese Knotweed from the Council
owned land at Mersey Road North (MRN).
The start of works was delayed due to Covid-19 and subsequently
began in late July 2020.The contractor has now advised of a
significant increase in the scope of the works and is claiming
additional costs.
RESOLVED - That:
Option 1 – The Council to fund the additional cost of the
Japanese Knotweed removal works at an additional cost of
£69,000.
Option 1 – The Council to fund the
additional cost of the Japanese Knotweed removal works at an
additional cost of £69,000.
Option 2 – The Council to reject the claim for additional
costs.
Option 2 – The Council to reject the
claim for additional costs.
Other reasons / organisations consulted
Hollinwood Junction Board Members.
Contact: Liz Garsrud, Principal Surveyor Email: liz.garsrud@oldham.gov.uk Email: liz.garsrud@oldham.gov.uk.
Publication date: 23/12/2020
Date of decision: 21/12/2020