Issue details

Metropolitan Place- ICT

To approve the ICT Cabling and ICT works in the Metropolitan Place project to enable 228 Social Work staff from Southlink Units 7-13 to all 5 floors of Metropolitan Place.
The value of the work is £56,603.61 and relates to the ICT materials and implementation costs for the proposed move in October and November 2019

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 04/10/2019

Decision due: 4 Oct 2019 by Deputy Chief Executive -

Lead member: Cabinet Member - Business, Employment and Enterprise

Contact: Stuart Barratt, Change Programme Manager 0161 770 3230, Email: stuart.barratt@oldham.gov.uk Email: stuart.barratt@oldham.gov.uk.

Consultation process

Children's services, ICT, HR, Legal Services, Finance and Property have been consulted on the proposals and this has been approved by the Deputy Chief Executive.

Decisions