Approval has already been obtained for the
council acquisition of the gas holder site from National Grid and
also for the council to fund the full amount of the demolition
costs and therefore the purpose of the report is for information
only, to confirm the final demolition costs, which have been
assessed on an open book basis and to provide a brief explanation
for the increase in costs.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 12/06/2019
Decision due: 10 Jun 2019 by Cabinet Member - Business, Employment and Enterprise
Lead member: Cabinet Member - Business, Employment and Enterprise
Contact: Liz Garsrud, Principal Surveyor Ext: 4284 email liz.garsrud@oldham.gov.uk liz.garsrud@oldham.gov.uk.
Consultation process
CIPB