Issue details

Demolition and subsequent acquisition of the site of the redundant gas holder at Albert Street, Hollinwood Junction, Oldham

Approval has already been obtained for the council acquisition of the gas holder site from National Grid and also for the council to fund the full amount of the demolition costs and therefore the purpose of the report is for information only, to confirm the final demolition costs, which have been assessed on an open book basis and to provide a brief explanation for the increase in costs.

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 12/06/2019

Decision due: 10 Jun 2019 by Cabinet Member - Business, Employment and Enterprise

Lead member: Cabinet Member - Business, Employment and Enterprise

Contact: Liz Garsrud, Principal Surveyor Ext: 4284 email  liz.garsrud@oldham.gov.uk  liz.garsrud@oldham.gov.uk.