Issue details

Transport Capital Programme 2018/19: Creation of a New Scheme - Oldham Way Structures

This report details a new scheme to be included in the 2018/19 Transport Capital Programme in order to progress design works on the Oldham Way Structures scheme.
This report identifies the budget to enable the creation of a new scheme in the 2018/19 Transport Capital Programme and progress advanced design work on a scheme to refurbish the Oldham Way Structures (Manchester Street viaduct, Waterloo Street Bridge and Wellington Road Bridge). There is an aspiration to include this scheme in upcoming Department for Transport (DfT) Challenge Fund bid.

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 09/05/2018

Contact: Eleanor Sykes, Transportation Policy Officer 0161 770 1668, Email: eleanor.sykes@oldham.gov.uk Email: Eleanor.sykes@oldham.gov.uk.

Consultation process

Briefing notes to develop the scheme were prepared by Unity officers and presented at CIPB in September 2017 and December 2017.
Following this we were asked to identify an appropriate budget within the Transport Capital Programme to enable this work to begin.
This report identifies an appropriate budget within the transport capital programme to enable the works to be undertaken.

Decisions