12/10/2018 - Highways England Designated Fund Programme - A663 Broadway (Trunk Road) ref: 3440    Recommendations Approved

•The delivery of four Designated Funds schemes by Oldham Council on behalf of Highways England be noted;
•The creation of four scheme budgets within the 2018/19 transport capital programme with a total value of £230,000 in order to deliver these schemes be noted;
•The overall value of the 2018/19 transport capital programme increasing by £230,000 be noted;
•Improvements to the highway network in Oldham as outlined below are noted.

Decision Maker: Leader of the Council and Portfolio Holder for Reform and Regeneration

Decision published: 24/10/2018

Effective from: 02/11/2018

Decision:

RESOLVED - That:
Oldham Council deliver the Designated Fund Programme works on behalf of Highways England to the terms and conditions set out in the Section 6 Agreement between Oldham Council and Highways England;

Lead officer: Eleanor Sykes


12/10/2018 - Henshaw Street, Oldham - Carriageway Resurfacing ref: 3436    Recommendations Approved

This report seeks delegated approval of:
•The cost of resurfacing Henshaw Street
•The approval of the appointment of the contractor for the works.
The work forms part of the £6m Highway Investment Programme

Decision Maker: Deputy Chief Executive -

Decision published: 24/10/2018

Effective from: 02/11/2018

Decision:

RESOLVED - That:
the delegated approval for these works is accepted and that the contract for the works are awarded to J Hopkins Contractors Ltd

Lead officer: Nigel Molden


15/10/2018 - Wider Area Network ref: 3434    Recommendations Approved

To commit resources to the Wider Area Network scheme from within the approved ICT capital programme, now that detailed financial and implementation information is available in relation to the project.

Decision Maker: Cabinet Member - Finance and Corporate Resources

Decision published: 23/10/2018

Effective from: 31/10/2018

Decision:

RESOLVED - That:
the Deputy Leader and Cabinet Member for Finance and Corporate Resources approves commitment of resources to the Wider Area Network scheme from within the approved ICT capital programme.

Lead officer: Jit Kara


15/10/2018 - Transport Capital Programme 2018/19: Budget Update Report 2 ref: 3428    Recommendations Approved

This report details budget changes within the agreed 2018/19 transport capital programme that are required so the programme continues to reflect current priorities, budgets match expenditure and that take-up of available grant funding is maximised.

Decision Maker: Cabinet Member - Finance and Corporate Resources

Decision published: 17/10/2018

Effective from: 24/10/2018

Decision:

RESOLVED - That:
-Agree the required budget changes as outlined in Appendix A to this report so that the programme continues to reflect current priorities, budgets match expenditure and that take-up of available grant funding is maximised.
-Accept a contribution of £12k from the Saddleworth

Wards affected: (All Wards);

Lead officer: Eleanor Sykes


15/10/2018 - 2018-2022 Capital Programme Update and Rephasing as at 30 September 2018 ref: 3427    Recommendations Approved

To realign/rephase capital scheme budgets across the life and beyond the 2018-2022 capital programme.

Decision Maker: Cabinet Member - Finance and Corporate Resources

Decision published: 16/10/2018

Effective from: 24/10/2018

Decision:

RESOLVED - That:
the Deputy Leader and Cabinet Member for Finance

Lead officer: Jit Kara


12/10/2018 - Counthill Road, Oldham Carriageway Resurfacing ref: 3426    Recommendations Approved

This report seeks delegated approval of:
•The cost of resurfacing Counthill Road
•The approval of the appointment of the contractor for the works.
The work forms part of the Incentive Fund Programme

Decision Maker: Deputy Chief Executive -

Decision published: 16/10/2018

Effective from: 12/10/2018

Decision:

RESOLVED - That:
the delegated approval for these works is accepted and that the contract for the works are awarded to Tarmac Trading Ltd

Lead officer: Nigel Molden


12/10/2018 - Smallbrook Road, Shaw Carriageway Resurfacing ref: 3425    Recommendations Approved

This report seeks delegated approval of:
•The cost of resurfacing Smallbrook Road
•The approval of the appointment of the contractor for the works.
The work forms part of the Incentive Fund Programme

Decision Maker: Deputy Chief Executive -

Decision published: 16/10/2018

Effective from: 12/10/2018

Decision:

RESOLVED - That:
the delegated approval for these works is granted and that the contract for the work is awarded to Tarmac Trading Ltd

Lead officer: Nigel Molden


12/10/2018 - Park Bridge Road Carriageway Resurfacing ref: 3424    Recommendations Approved

This report seeks delegated approval of:
•The cost of resurfacing Park Bridge Road
•The approval of the appointment of the contractor for the works.
The work forms part of the £6m Highway Investment Programme

Decision Maker: Deputy Chief Executive -

Decision published: 16/10/2018

Effective from: 12/10/2018

Decision:

RESOLVED - That:
the delegated approval for these works is accepted and that the contract for the works is awarded to Tarmac Trading Ltd

Lead officer: Nigel Molden


05/10/2018 - Proposed Disabled Persons Parking Places Order - Various Locations ref: 3423    Recommendations Approved

The purpose of the report is to seek approval to implement disabled persons parking places at various locations around the Borough.

Decision Maker: Deputy Chief Executive -

Decision published: 12/10/2018

Effective from: 20/10/2018

Decision:

RESOLVED - That:
the proposed disabled bays detailed in the Schedule at the end of the report be introduced

Lead officer: Jeannette Whitney


05/10/2018 - Proposed Prohibition of Waiting - Block Lane, Chadderton, Oldham ref: 3422    Recommendations Approved

The purpose of this report is to consider a request received from a resident of the Block Lane area via the elected MP for the introduction of prohibitive waiting restrictions on Block Lane at its junction with Hampshire Road, to alleviate obstructive parking taking place

Decision Maker: Deputy Chief Executive -

Decision published: 12/10/2018

Effective from: 20/10/2018

Decision:

RESOLVED - That:
no waiting at any time (double yellow lines) restrictions be introduced on Block Lane and Hampshire Road in accordance with the schedule at the end of this report

Lead officer: Darryll Elwood


04/10/2018 - Alignment of Bulky Bobs contract with the Council?s fees & charges timelines ref: 3421    Recommendations Approved

Authorisation is required to extend the current contract with Bulky Bob?s by 3 months to bring the contract timescales in line with the financial year and the Council?s fees

Decision Maker: Deputy Chief Executive -

Decision published: 04/10/2018

Effective from: 04/10/2018

Decision:

RESOLVED - That:
Authorisation has been given to extend the current contract with Bulky Bob’s by 3 months.

Lead officer: Mark Husdan


03/10/2018 - Annie Kenney Statue ref: 3420    Recommendations Approved

To ensure that the statue of Annie Kenney is installed in 2018 to commemorate the centenary year of the Representation of the People Act.
The Annie Kenney Memorial Fund Committee is proposing to gift the Council with the money that has been raised through their public funding efforts. This to date totals £24k.
The money will be given to the Council without condition.
The Council proposes to use the money to install a statue of Annie Kenney in Oldham Town Centre, as part of commemorating the centenary year of the Representation of the People Act.
The Council intends to commission the statue and take ownership and responsibility of the asset, as part of the public realm within Oldham Town Centre.
As part of the regeneration of the Old Town Hall, a public square was built and a plinth was installed at the steps of the Old Town Hall, where it is proposed that the statue of Annie Kenney will be homed.
The total cost of the statue is £30,143 and the Annie Kenney Memorial Fund Committee is continuing fundraising efforts whilst the commissioning and installation of the statue commences, in order to ensure that the Council receives the full costs required.
It is proposed to commission Leander Architectural to produce the statue, because the design maquette has already been prepared by this company and approved by the Annie Kenney Memorial Fund Committee. Therefore, the Council in taking the project forward, would need to commission the statue from the same company. In light of this, it is proposed to seek an exemption from the Contract Procedure Rules under Rules 21.3 (a) and 21.3 (c) so that Leander Architectural can be commissioned to create the Annie Kenney statue.
It is also proposed that the Council will support an opening launch by having some Annie Kenney material on display in our WW1 exhibition that should coincide with the unveiling.
The statue will be placed on the Council’s asset register and the ongoing maintenance will be funded through the Town Centre Management budget, like other public art in the town.

Decision Maker: Cabinet Member - Business, Employment and Enterprise

Decision published: 04/10/2018

Effective from: 03/10/2018

Decision:

RESOLVED - That an exemption from the Council’s Contract Procedure Rules be approved under Rules 21.3 (a) and 21.3 (c) and that Leander Architectural be commissioned to create the statue of Annie Kenney.

Lead officer: Heather Moore


02/10/2018 - Exemption from Contract Procedure Rules for the appointment of a heritage project contracts services in relation to Oldham Heritage and Arts Centre ref: 3419    Recommendations Approved

To seek exemption from the Contract Procedure Rules under regulation 21.3 paragraphs (c), (e) and (h) of the Contract Procedure Rules in that the Services which are required are of a specialist nature and the provision of the service is urgently required.

Decision Maker: Deputy Chief Executive -

Decision published: 02/10/2018

Effective from: 02/10/2018

Decision:

RESOLVED - That:
To seek exemption from the Contract Procedure Rules to enter directly into contract with a Heritage Specialist for the provision of professional surveying services in respect of heritage elements of the Oldham Heritage and Arts Centre. The surveying services are to be performed are found in appendix 1