12/10/2018 - Highways England Designated Fund Programme - A663 Broadway (Trunk Road) ref: 3440 Recommendations Approved
•The delivery of four Designated Funds
schemes by Oldham Council on behalf of Highways England be
noted;
•The creation of four scheme budgets within the 2018/19
transport capital programme with a total value of £230,000 in
order to deliver these schemes be noted;
•The overall value of the 2018/19 transport capital programme
increasing by £230,000 be noted;
•Improvements to the highway network in Oldham as outlined
below are noted.
Decision Maker: Leader of the Council and Portfolio Holder for Reform and Regeneration
Decision published: 24/10/2018
Effective from: 02/11/2018
Decision:
RESOLVED - That:
Oldham Council deliver the Designated Fund Programme works on
behalf of Highways England to the terms and conditions set out in
the Section 6 Agreement between Oldham Council and Highways
England;
Lead officer: Eleanor Sykes
12/10/2018 - Henshaw Street, Oldham - Carriageway Resurfacing ref: 3436 Recommendations Approved
This report seeks delegated approval of:
•The cost of resurfacing Henshaw Street
•The approval of the appointment of the contractor for the
works.
The work forms part of the £6m Highway Investment
Programme
Decision Maker: Deputy Chief Executive -
Decision published: 24/10/2018
Effective from: 02/11/2018
Decision:
RESOLVED - That:
the delegated approval for these works is accepted and that the
contract for the works are awarded to J Hopkins Contractors
Ltd
Lead officer: Nigel Molden
15/10/2018 - Wider Area Network ref: 3434 Recommendations Approved
To commit resources to the Wider Area Network
scheme from within the approved ICT capital programme, now that
detailed financial and implementation information is available in
relation to the project.
Decision Maker: Cabinet Member - Finance and Corporate Resources
Decision published: 23/10/2018
Effective from: 31/10/2018
Decision:
RESOLVED - That:
the Deputy Leader and Cabinet Member for Finance and Corporate
Resources approves commitment of resources to the Wider Area
Network scheme from within the approved ICT capital
programme.
Lead officer: Jit Kara
15/10/2018 - Transport Capital Programme 2018/19: Budget Update Report 2 ref: 3428 Recommendations Approved
This report details budget changes within the
agreed 2018/19 transport capital programme that are required so the
programme continues to reflect current priorities, budgets match
expenditure and that take-up of available grant funding is
maximised.
Decision Maker: Cabinet Member - Finance and Corporate Resources
Decision published: 17/10/2018
Effective from: 24/10/2018
Decision:
RESOLVED - That:
-Agree the required budget changes as outlined in Appendix A to
this report so that the programme continues to reflect current
priorities, budgets match expenditure and that take-up of available
grant funding is maximised.
-Accept a contribution of £12k from the Saddleworth
Wards affected: (All Wards);
Lead officer: Eleanor Sykes
15/10/2018 - 2018-2022 Capital Programme Update and Rephasing as at 30 September 2018 ref: 3427 Recommendations Approved
To realign/rephase capital scheme budgets
across the life and beyond the 2018-2022 capital programme.
Decision Maker: Cabinet Member - Finance and Corporate Resources
Decision published: 16/10/2018
Effective from: 24/10/2018
Decision:
RESOLVED - That:
the Deputy Leader and Cabinet Member for Finance
Lead officer: Jit Kara
12/10/2018 - Counthill Road, Oldham Carriageway Resurfacing ref: 3426 Recommendations Approved
This report seeks delegated approval of:
•The cost of resurfacing Counthill Road
•The approval of the appointment of the contractor for the
works.
The work forms part of the Incentive Fund Programme
Decision Maker: Deputy Chief Executive -
Decision published: 16/10/2018
Effective from: 12/10/2018
Decision:
RESOLVED - That:
the delegated approval for these works is accepted and that the
contract for the works are awarded to Tarmac Trading Ltd
Lead officer: Nigel Molden
12/10/2018 - Smallbrook Road, Shaw Carriageway Resurfacing ref: 3425 Recommendations Approved
This report seeks delegated approval of:
•The cost of resurfacing Smallbrook Road
•The approval of the appointment of the contractor for the
works.
The work forms part of the Incentive Fund Programme
Decision Maker: Deputy Chief Executive -
Decision published: 16/10/2018
Effective from: 12/10/2018
Decision:
RESOLVED - That:
the delegated approval for these works is granted and that the
contract for the work is awarded to Tarmac Trading Ltd
Lead officer: Nigel Molden
12/10/2018 - Park Bridge Road Carriageway Resurfacing ref: 3424 Recommendations Approved
This report seeks delegated approval of:
•The cost of resurfacing Park Bridge Road
•The approval of the appointment of the contractor for the
works.
The work forms part of the £6m Highway Investment
Programme
Decision Maker: Deputy Chief Executive -
Decision published: 16/10/2018
Effective from: 12/10/2018
Decision:
RESOLVED - That:
the delegated approval for these works is accepted and that the
contract for the works is awarded to Tarmac Trading Ltd
Lead officer: Nigel Molden
05/10/2018 - Proposed Disabled Persons Parking Places Order - Various Locations ref: 3423 Recommendations Approved
The purpose of the report is to seek approval
to implement disabled persons parking places at various locations
around the Borough.
Decision Maker: Deputy Chief Executive -
Decision published: 12/10/2018
Effective from: 20/10/2018
Decision:
RESOLVED - That:
the proposed disabled bays detailed in the Schedule at the end of
the report be introduced
Lead officer: Jeannette Whitney
05/10/2018 - Proposed Prohibition of Waiting - Block Lane, Chadderton, Oldham ref: 3422 Recommendations Approved
The purpose of this report is to consider a
request received from a resident of the Block Lane area via the
elected MP for the introduction of prohibitive waiting restrictions
on Block Lane at its junction with Hampshire Road, to alleviate
obstructive parking taking place
Decision Maker: Deputy Chief Executive -
Decision published: 12/10/2018
Effective from: 20/10/2018
Decision:
RESOLVED - That:
no waiting at any time (double yellow lines) restrictions be
introduced on Block Lane and Hampshire Road in accordance with the
schedule at the end of this report
Lead officer: Darryll Elwood
04/10/2018 - Alignment of Bulky Bobs contract with the Council?s fees & charges timelines ref: 3421 Recommendations Approved
Authorisation is required to extend the
current contract with Bulky Bob?s by 3 months to bring the contract
timescales in line with the financial year and the Council?s
fees
Decision Maker: Deputy Chief Executive -
Decision published: 04/10/2018
Effective from: 04/10/2018
Decision:
RESOLVED - That:
Authorisation has been given to extend the current contract with
Bulky Bob’s by 3 months.
Lead officer: Mark Husdan
03/10/2018 - Annie Kenney Statue ref: 3420 Recommendations Approved
To ensure that the statue of Annie Kenney is
installed in 2018 to commemorate the centenary year of the
Representation of the People Act.
The Annie Kenney Memorial Fund Committee is proposing to gift the
Council with the money that has been raised through their public
funding efforts. This to date totals £24k.
The money will be given to the Council without condition.
The Council proposes to use the money to install a statue of Annie
Kenney in Oldham Town Centre, as part of commemorating the
centenary year of the Representation of the People Act.
The Council intends to commission the statue and take ownership and
responsibility of the asset, as part of the public realm within
Oldham Town Centre.
As part of the regeneration of the Old Town Hall, a public square
was built and a plinth was installed at the steps of the Old Town
Hall, where it is proposed that the statue of Annie Kenney will be
homed.
The total cost of the statue is £30,143 and the Annie Kenney
Memorial Fund Committee is continuing fundraising efforts whilst
the commissioning and installation of the statue commences, in
order to ensure that the Council receives the full costs
required.
It is proposed to commission Leander Architectural to produce the
statue, because the design maquette has already been prepared by
this company and approved by the Annie Kenney Memorial Fund
Committee. Therefore, the Council in taking the project forward,
would need to commission the statue from the same company. In light
of this, it is proposed to seek an exemption from the Contract
Procedure Rules under Rules 21.3 (a) and 21.3 (c) so that Leander
Architectural can be commissioned to create the Annie Kenney
statue.
It is also proposed that the Council will support an opening launch
by having some Annie Kenney material on display in our WW1
exhibition that should coincide with the unveiling.
The statue will be placed on the Council’s asset register and
the ongoing maintenance will be funded through the Town Centre
Management budget, like other public art in the town.
Decision Maker: Cabinet Member - Business, Employment and Enterprise
Decision published: 04/10/2018
Effective from: 03/10/2018
Decision:
RESOLVED - That an exemption from the
Council’s Contract Procedure Rules be approved under Rules
21.3 (a) and 21.3 (c) and that Leander Architectural be
commissioned to create the statue of Annie Kenney.
Lead officer: Heather Moore
02/10/2018 - Exemption from Contract Procedure Rules for the appointment of a heritage project contracts services in relation to Oldham Heritage and Arts Centre ref: 3419 Recommendations Approved
To seek exemption from the Contract Procedure
Rules under regulation 21.3 paragraphs (c), (e) and (h) of the
Contract Procedure Rules in that the Services which are required
are of a specialist nature and the provision of the service is
urgently required.
Decision Maker: Deputy Chief Executive -
Decision published: 02/10/2018
Effective from: 02/10/2018
Decision:
RESOLVED - That:
To seek exemption from the Contract Procedure Rules to enter
directly into contract with a Heritage Specialist for the provision
of professional surveying services in respect of heritage elements
of the Oldham Heritage and Arts Centre. The surveying services are
to be performed are found in appendix 1
Lead officer: Brian Enright