Decision Maker: Deputy Chief Executive -
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
This report seeks delegated approval of:
•The cost of resurfacing A627 Chadderton Way
•The approval of the appointment of the contractor for the
works.
The work forms part of the Highway Investment Programme
RESOLVED - That:
delegated approval for the surfacing A627 Chadderton Way is
accepted and the contract for the works be awarded to Kier Group
PLC
Option 1 - Approve the tender award to Kier
Group plc for the surfacing of A627 Chadderton Way in line with
Oldham Council’s Contract Procedure Rules
Option 2 - Do not approve the tender award to Kier Group plc for
the surfacing of A627 Chadderton Way, in line with Oldham
Council’s Contract Procedure Rules
Option 2
Other reasons / organisations consulted
Not applicable
Contact: Matthew McGreal, Assistant Engineer 0161 770 1955 Email: Matthew.McGreal@unitypartnership.com.
Publication date: 12/06/2019
Date of decision: 11/06/2019
Effective from:
Current call-in Count: 0