The purpose of the report is to seek approval
for the Council to appoint Environmental Engineering Partnership
Limited (trading as 'e3p') to carry out some additional site
investigation works on the Council's retained land to the rear of
the former Breeze Hill School.
RESOLVED - That the Council appoint e3p via
the Bloom framework.
Option 1 - Competitively tender the
opportunity for a suitable contractor to carry out the remaining
site investigation works.
Option 2 - Appoint RPS to complete the site investigation
works.
Option 3 - Appoint e3p to complete the site investigation
works.
Option 1 - Competitively tender the
opportunity for a suitable contractor to carry out the remaining
site investigation works.
Option 2 - Appoint RPS to complete the site investigation
works.
Other reasons / organisations consulted
Ward Cllrs have been consulted on the proposed
development of the land on 9 April 2019 and 10 June 2019.
Discussions have also taken place with both legal and audit
colleagues.