Obtain approval for the cost of Broomes Park
Flood Alleviation Phase 1 Scheme and for the approval of the
appointment of the Contractor for the works. Costs for the scheme
were obtained by framework tender, the Council’s procurement
process
RESOLVED - That:
the Contract for the works is awarded to Westshield Ltd
Option 1 - The preferred option would be to
award the scheme of Broomes Park Flood Alleviation Phase 1 to
Westshield Ltd. The implementation of the scheme is essential to
alleviate against flooding to the properties on North Dene Park and
Broomes Park
Option 2 - The alternative would be not to proceed with the works,
which will leave the Council open to potential claims by residents
of North Dene Park and Broomes Park whose properties currently
flood as a result of ground water and surface water run-off from an
adjacent embankment (Oldham Council land)
Option 2
Other reasons / organisations consulted
Not applicable
Contact: Jeannette Whitney, Technical Support Admin 0161 770 4372 Email: jeanette.whitney@oldham.gov.uk.