Decision Maker: Executive Director for Place & Economic Growth
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The purpose of the report is to seek approval
for the Council to appoint Reddish Demolition Limited to complete
the demolition of the former Failsworth Youth Centre in accordance
with the agreed specification and permission granted under
reference DM/342626/18.
RESOLVED - That the Council seek to enter into
a contract with Reddish Demolition Limited for the clearance of the
former Failsworth Youth Centre in accordance with the tendered
specification which has similarly been approved by the Planning
Authority under reference DM/342626/18.
Option 1 - Do Nothing.
Option 2 - Accept the most economically advantageous tender.
Option 1 - Do Nothing.
Other reasons / organisations consulted
- Demolition Notice approved by Planning
Authority on 21 December 2018.
- Ward Councillors consulted on 21 January 2019.
- Cabinet Member briefed on 30 August 2018.
Contact: Mark Prestwich, Development Officer 0161 770 1660, Email: mark.prestwich@oldham.gov.uk Email: Mark.Prestwich@oldham.gov.uk.
Publication date: 21/01/2019
Date of decision: 21/01/2019
Accompanying Documents: