Growth Deal 3 Major Scheme: Oldham Town Centre Regeneration and Connectivity – appointment of external programme management support

Decision Maker: Deputy Chief Executive -

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To seek delegated approval for an exemption from Oldham Council’s Contract Procedure Rules to directly appoint a consultant to provide programme management support for the Growth Deal 3 Major Scheme: Oldham Town Centre Regeneration and Connectivity.

Decision:

RESOLVED - That:
An exemption from the Council’s contract procedure rules to appoint the preferred consultant to provide programme management support for the Growth Deal 3 Major Scheme: Oldham Town Centre Regeneration and Connectivity was approved.

Reasons for the decision:

Option 1
To reject the exemption and not appoint a consultant directly.
Option 2
To go out to tender to procure programme management support for the Growth Deal 3 Major Scheme: Oldham Town Centre Regeneration and Connectivity.

Alternative options considered:

Option 2

Other reasons / organisations consulted

N/a

Contact: Joanne Betts, Interim Manager - Stratgeic Transport 0161 770 4346 Email: joanne.betts@oldham.gov.uk Email: joanne.betts@oldham.gov.uk.

Publication date: 01/11/2018

Date of decision: 27/09/2018