This report seeks delegated approval of:
•The cost of resurfacing Peel Street
•The approval of the appointment of the contractor for the
works.
The work forms part of the £6m Highway Investment
Programme
RESOLVED - That:
the delegated approval for these works is accepted and that the
contract for the works are awarded to J Hopkins Contractors
Ltd
Option 1 - Approve the tender award to J
Hopkins Contractors Ltd for the resurfacing of Peel Street in line
with Oldham Council’s Contract Procedure Rules
Option 2 - Do not approve the tender award to J Hopkins Contractors
Ltd for the resurfacing of Peel Street, in line with Oldham
Council’s Contract Procedure Rules
Option 2
Other reasons / organisations consulted
Not applicable
Contact: Nigel Molden, Senior Engineer 0161 770 1952 Email: nigel.molden@unitypartnetship..com.
Publication date: 23/10/2018
Date of decision: 23/10/2018
Accompanying Documents: