Decision details

A663 Big Lamp Roundabout

Decision Maker: Deputy Chief Executive -

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

This report seeks delegated approval of:
•The cost of resurfacing A663 Big Lamp Roundabout;
•The approval of the appointment of the contractor for the works.
The work forms part of the £6m Highway Investment Programme

Decision:

RESOLVED - That:
the delegated approval for these works is accepted and that the contract for the works are awarded to J Hopkins Contractors Ltd

Reasons for the decision:

Option 1 - approve the tender award to J Hopkins Contractors Ltd for the resurfacing of A663 Big Lamp Roundabout in line with Oldham Council’s Contract Procedure Rules
Option 2 - do not approve the tender award to J Hopkins Contractors Ltd for the resurfacing of A663 Big Lamp Roundabout in line with Oldham Council’s Contract Procedure Rules

Alternative options considered:

Option 2

Other reasons / organisations consulted

Not applicable

Contact: Richard Edwards, Principal Engineer 0161 770 1692 Email: Richard.Edwards@unitypartnership.com.

Publication date: 22/06/2018

Date of decision: 20/06/2018