Purpose:
This report seeks delegated approval of:
•The cost of Micro Surfacing;
•The approval of the appointment of the contractor for the
works.
The work forms part of the £6m Highway Investment
Programme
Decision:
RESOLVED - That:
the delegated approval for these works is accepted and that the
contract for the works are awarded to Kier Highways Ltd
Reasons for the decision:
Option 1 - Approve the tender award to Kier
Highways Ltd for the Micro Surfacing in line with Oldham
Council’s Contract Procedure Rules.
Option 2 -
Do not approve the tender award to Kier Highways Ltd for the Micro
Surfacing in line with Oldham Council’s Contract Procedure
Rules.
Alternative options considered:
Option 2
Other reasons / organisations consulted
The Highways Investment Programme 2018 has
been approved centrally at Cabinet following involvement from Unity
Officers at a senior level, the Leader and Deputy Leader and other
members of Capital Investment Programme Board (CIPB)
Contact: Richard Edwards, Principal Engineer 0161 770 1692 Email: Richard.Edwards@unitypartnership.com.
Publication date: 15/06/2018
Date of decision: 18/05/2018
Effective from: 23/06/2018