Decision details

Exemption from Contract Procedure Rules (King Street Footbridge - Phase 1 Refurbishment)

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

Obtain approval for an exemption from Oldham Council’s contract procedure rules for a Contract to be awarded within the transport capital programme

Decision:

RESOLVED - That:
Construction works to Middleton Road Bridge, an overbridge on the A627 Oldham Way bypass are currently underway. The location of King Street Footbridge is within the scheme extents of the Middleton Road Bridge scheme.
For the procurement of the works to King Street Footbridge – Phase 1 Refurbishment, an exemption is requested under clause 21.3 (h) of the contract procedure rules document. The grounds for requesting this exemption are:
•The execution of the Works are required in circumstances of extreme urgency where immediate repairs are required to the structure damaged by vandalism;
•This option reduces staff time and associated costs and ensures delivery of the Works to make the structure safe in the short-term;
•Reduces delivery costs on preliminaries by approaching the Middleton Road Bridge Contactor (Eric Wright Civil Engineering Ltd) directly and making use of the Middleton Road Bridge scheme site compound and welfare facilities;
•Reduces delays and costs to the Middleton Road Bridge scheme by approaching Eric Wright Civil Engineering Ltd to programme the Works to not impact on the Middleton Road Bridge scheme;
•Reduces delivery costs of awarding Works to two different contractors. Eric Wright Civil Engineering Ltd would charge for an overhead cost to manage another Contractor within the scheme extents of Middleton Road Bridge;
Reduces delay in construction of the Works by up to 8 months by eliminating the need to wait for the completion of the Middleton Road Bridge scheme.

Reasons for the decision:

Option 1 - to approve the exemption from the Council’s contract procedure rules for the element detailed in this report
Option 2 - to reject the exemption and to apply traditional procurement procedures. This will cause unacceptable delay to delivery, while funding is available and leave the structure unsafe for an additional 8 month period

Alternative options considered:

Option 2

Other reasons / organisations consulted

Town Centre Management

Contact: Jeannette Whitney, Technical Support Admin 0161 770 4372 Email: jeanette.whitney@oldham.gov.uk.

Publication date: 21/03/2018

Date of decision: 20/03/2018