Decision details

Royton Town Hall & Library

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decisions:

Consideration was given to the commercially sensitive information in relation to Item 13 Royton Town Hall.

 

RESOLVED – That:

1.    The refurbishment works as set out in this report approved.

2.    The increased project cost caused by the national impact of inflation on materials and construction services be noted.

3.    The additional funding needed to deliver the project be approved.

4.    The appointment of the successful contractor following the completion of the tender process be approved.

5.    Approval be given for the contractual, financial and project delivery to be delegated to the Executive Director of Place and Growth in consultation with the Cabinet Member for Finance and Low Carbon. 

 

Publication date: 15/02/2023

Date of decision: 13/02/2023

Decided at meeting: 13/02/2023 - Cabinet

Effective from: 23/02/2023

Accompanying Documents: